736-736 1/2 W 75TH ST 90044
Certificate Information: 736-736 1/2 W 75TH ST 90044
- Application / Permit
- 22010-10000-02489
- Plan Check / Job No.
- B22LA09171
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan : NEW 2-STORY DUPLEX. (BUILDING "A")
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Current Status
- CofO Issued on 8/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | GARO TELMI |
| Corrections Issued | 6/21/2022 | GARO TELMI |
| Quality Review Completed | 6/28/2022 | CHAD DOI |
| Plan Check Approved | 1/13/2023 | GARO TELMI |
| Issued | 1/25/2023 | APPLICANT |
| CofO in Progress | 8/7/2023 | MICHAEL LEWIS |
| CofO Issued | 8/9/2023 | DEROLD HAUFF |
| Permit Finaled | 8/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| SB8 RUD | Cleared | 6/23/2022 | JAMES MCCARTHY |
| Address approval | Cleared | 7/6/2022 | WALLIE JONG |
| Highway dedication | Cleared | 7/6/2022 | WALLIE JONG |
| Permit | Cleared | 7/6/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | WALLIE JONG |
| Sewer availability | Cleared | 7/7/2022 | WALLIE JONG |
| "Q" conditions | Cleared | 7/8/2022 | SPENCER WEJROWSKI |
| Frnt yard landscape/Water mgmt | Cleared | 7/8/2022 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 7/15/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 8/5/2022 | KURT CORRAL |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/7/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 3/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 3/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/28/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/12/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 5/12/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 5/15/2023 | Approved | MICHAEL LEWIS |
| Insulation | 5/18/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/1/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/1/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/14/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/28/2023 | Approved | MICHAEL LEWIS |
| Green Building Final | 7/28/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 7/28/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 7/28/2023 | Approved | MICHAEL LEWIS |
| Final | 8/2/2023 | OK to Issue CofO | MICHAEL LEWIS |
| PLUMBING-Final | 8/2/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 8/2/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 8/4/2023 | Approved | MICHAEL LEWIS |