4651 N MORSE AVE 91423
Certificate Information: 4651 N MORSE AVE 91423
- Application / Permit
- 22010-10000-02488
- Plan Check / Job No.
- B22LA09170
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED 1 CAR GARAGE.
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Current Status
- CofO Issued on 10/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | GARO TELMI |
| Corrections Issued | 6/26/2022 | GARO TELMI |
| Quality Review Completed | 7/6/2022 | CHAD DOI |
| Applicant returned to address corrections | 2/17/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/22/2023 | GARO TELMI |
| Plan Check Approved | 5/11/2023 | GARO TELMI |
| Issued | 6/13/2023 | APPLICANT |
| CofO in Progress | 10/2/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/21/2024 | DANIEL ORRANTE |
| CofO Issued | 10/21/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/21/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Permit | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 8/5/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 8/13/2022 | RUEL COLE |
| Low Impact Development | Cleared | 9/7/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/7/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/7/2022 | LEE GUILBEAUX |
| ZI | Cleared | 11/17/2022 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/12/2023 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 7/12/2023 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 7/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 7/26/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/18/2023 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 9/19/2023 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 10/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 11/7/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 11/9/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 11/14/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 11/21/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/30/2023 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 11/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/7/2023 | Partial Approval | JOHN COLEMAN |
| Insulation | 12/14/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/22/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 1/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 5/23/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/27/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 6/27/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/30/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/30/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Final | 7/30/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/30/2024 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 7/30/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/1/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 10/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/2/2024 | Approved | CHRISTOPHE COCHRAN |