2635 S VINEYARD AVE 90016

Certificate Information: 2635 S VINEYARD AVE 90016

Application / Permit
22010-10000-02479
Plan Check / Job No.
B22LA09138
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TYPE V-B ADU New Construction, Detached, 1 story, 2Bed, 2Bath, Living room, Kitchen, and Laundry Room. Total SF 744 SF PER Ordinance and LAMC 12.22 A 33(c) &(d).
Permit Issued
Issued on 3/6/2023
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 ZAW HAN
Corrections Issued 5/24/2022 ZAW HAN
Applicant returned to address corrections 1/20/2023 ZAW HAN
Plan Check Approved 1/27/2023 ZAW HAN
Issued 3/6/2023 APPLICANT
CofO in Progress 9/25/2023 CALEB MEISTER
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/31/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/23/2022 JEANIE LAM
Sewer availability Cleared 6/23/2022 JEANIE LAM
Construction near power lines Cleared 8/19/2022 RIDWAN HARDY
Low Impact Development Cleared 12/16/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/27/2022 AMAAN MALIK

Contact Information

Contractor Molinas Construction Services; Lic. No.: 1091636-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/13/2023 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 3/17/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 3/17/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 4/13/2023 Not Ready for Inspection CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 4/13/2023 Approved CALEB MEISTER
Deputy Wood Construction 4/17/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 4/19/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 4/19/2023 Approved MICHAEL LEWIS
Green Building Rough 4/19/2023 Approved MICHAEL LEWIS
HVAC-Rough 4/19/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 4/19/2023 Approved MICHAEL LEWIS
MERV13>=Rough 4/19/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 4/19/2023 Approved MICHAEL LEWIS
Insulation 4/25/2023 Corrections Issued CALEB MEISTER
Drywall Nailing 5/1/2023 Approved CALEB MEISTER
Insulation 5/1/2023 Approved CALEB MEISTER
Sewer 5/12/2023 Approved CALEB MEISTER
Underground Mechanical 6/13/2023 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 7/14/2023 Approved CALEB MEISTER
Final 7/14/2023 Corrections Issued CALEB MEISTER
Footing/Foundation/Slab 7/14/2023 Approved CALEB MEISTER
MERV13>=Final 7/14/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Not Ready CALEB MEISTER
Service/Power Release 7/14/2023 Not Ready for Inspection CALEB MEISTER
Smoke Detectors 7/14/2023 Approved CALEB MEISTER
Final 7/26/2023 Corrections Issued CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved CALEB MEISTER
Service/Power Release 7/26/2023 Not Ready for Inspection CALEB MEISTER
Final 8/9/2023 Not Ready for Inspection CALEB MEISTER
Service/Power Release 8/9/2023 Not Ready for Inspection CALEB MEISTER
Final 9/25/2023 OK to Issue CofO CALEB MEISTER
Service/Power Release 9/25/2023 Approved CALEB MEISTER