2878 W AVENUE 33 90065
Certificate Information: 2878 W AVENUE 33 90065
- Application / Permit
- 22010-10000-02478
- Plan Check / Job No.
- B22LA09137
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* Proposed detached accessory dwelling unit per ordinance. LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/2/2023
- Issuing Office
- Current Status
- CofO Issued on 10/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | MICHAEL LOPEZ |
| Corrections Issued | 5/20/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/6/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/18/2023 | HANS SANTIAGO |
| Plan Check Approved | 7/23/2023 | MICHAEL LOPEZ |
| No Progress | 8/1/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 8/1/2023 | MICHAEL LOPEZ |
| No Progress | 8/1/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 8/1/2023 | MICHAEL LOPEZ |
| Issued | 8/2/2023 | APPLICANT |
| CofO in Progress | 10/3/2024 | THOMAS LOGRASSO |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
| CofO Issued | 10/16/2024 | RUBEN SALAS |
| Permit Finaled | 10/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 6/2/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 11/3/2022 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 3/30/2023 | SERGIO VALENZUELA |
| Low Impact Development | Cleared | 5/5/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/26/2023 | HUGO LOPEZ |
| Supp. Use District POD/CDO/TDO | Cleared | 7/17/2023 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | , |
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/12/2023 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 9/19/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/22/2023 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/2/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/18/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/5/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/5/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/14/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/14/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/23/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/23/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 2/23/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/28/2024 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/4/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 3/4/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 3/5/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Shower Pan | 3/5/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/8/2024 | Approved | LILIANA PORTILLO |
| Insulation | 3/8/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/30/2024 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 6/14/2024 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 6/14/2024 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 6/20/2024 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 6/20/2024 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 6/25/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 7/1/2024 | Partial Approval | BRENDAN MORELLI |
| Final | 8/7/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/12/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 9/5/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/5/2024 | Approved | THOMAS LOGRASSO |
| Green Building Final | 9/5/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 9/5/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 9/5/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 9/5/2024 | Approved | THOMAS LOGRASSO |
| Final | 9/12/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 9/12/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 10/2/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 10/2/2024 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 10/2/2024 | Approved | THOMAS LOGRASSO |