2134 S MAGNOLIA CT 90007
Certificate Information: 2134 S MAGNOLIA CT 90007
- Application / Permit
- 22010-10000-02477
- Plan Check / Job No.
- B22LA09136
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO AND CONVERT EXISTING GARAGE TO ADU PER LAMC 12.22 A.33(C)(D) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | KHUONG TRUONG |
| Corrections Issued | 5/20/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 12/22/2022 | KHUONG TRUONG |
| Plan Check Approved | 1/11/2023 | KHUONG TRUONG |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 8/22/2024 | WILLIAM SIERRA |
| CofO Issued | 9/17/2024 | DEROLD HAUFF |
| Permit Finaled | 9/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 6/24/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 6/24/2022 | ANACANY HURTADO |
| Address approval | Cleared | 6/27/2022 | STEVE MELGAR |
| "Q" conditions | Cleared | 6/28/2022 | ANACANY HURTADO |
| ZI | Cleared | 6/28/2022 | ANACANY HURTADO |
| ZI | Cleared | 6/28/2022 | ANACANY HURTADO |
| Permit | Cleared | 6/29/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 7/13/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 7/20/2022 | MICHAEL SOTO |
| HPOZ | Cleared | 12/14/2022 | MICAELA TORRES-GIL |
| Roof/Waste drainage to street | Cleared | 12/16/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yiu,, Siu Fung; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/8/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 3/8/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/14/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 3/15/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/16/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/20/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/24/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 4/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/13/2023 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/13/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/13/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/13/2023 | Corrections Issued | STUART CHAPMAN |
| MERV13>=Rough | 6/13/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/13/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 6/13/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 6/20/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 6/21/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 6/28/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/3/2023 | Partial Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/14/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/14/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/14/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 7/17/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Insulation | 7/26/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 8/16/2023 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 9/7/2023 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 9/7/2023 | Corrections Issued | RONNIE MINDANAO |
| Shower Pan | 10/13/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 11/20/2023 | Approved | KATHRYN BUTTERWORTH |
| Final | 11/20/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 11/20/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 11/20/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/29/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 11/29/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/29/2023 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 11/29/2023 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 11/29/2023 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 11/29/2023 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | WILLIAM SIERRA |
| Final | 8/13/2024 | OK to Issue CofO | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Approved | WILLIAM SIERRA |