2641 S HARCOURT AVE 90016
Certificate Information: 2641 S HARCOURT AVE 90016
- Application / Permit
- 22010-10000-02473
- Plan Check / Job No.
- B22LA09129
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED STORAGE, GARAGE AND POOL BATHROOM
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | KHUONG TRUONG |
| Corrections Issued | 5/22/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Plan Check Approved | 6/3/2022 | KHUONG TRUONG |
| Plan Check Approved | 8/24/2022 | ALDO UBAU |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 6/30/2023 | CALEB MEISTER |
| Permit Finaled | 8/10/2023 | DEROLD HAUFF |
| CofO Issued | 8/10/2023 | DEROLD HAUFF |
| Permit Finaled | 8/10/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| Roof/Waste drainage to street | Cleared | 5/27/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2022 | CELINA MORENO |
Contact Information
| Contractor | Vision Home Remodeling Inc; Lic. No.: 1059278-B | 20500 ARCHWOOD ST CANOGA PARK, CA 91306 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/20/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 2/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| Deputy Wood Construction | 2/2/2023 | Conditional Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2023 | Corrections Issued | CALEB MEISTER |
| Deputy Wood Construction | 2/10/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 2/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 2/16/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Not Ready for Inspection | CALEB MEISTER |
| Underground Mechanical | 2/17/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | CALEB MEISTER |
| Final | 6/26/2023 | OK to Issue CofO | CALEB MEISTER |
| Footing/Foundation/Slab | 6/26/2023 | Approved | CALEB MEISTER |
| Green Building Final | 6/26/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 6/26/2023 | Approved | CALEB MEISTER |
| MERV13>=Final | 6/26/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 6/26/2023 | Approved | CALEB MEISTER |
| Smoke Detectors | 6/26/2023 | Approved | CALEB MEISTER |