Pre-Inspection
|
8/8/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Grading
|
8/18/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Grading
|
9/5/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Grading
|
9/6/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
9/6/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
9/7/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/7/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
9/7/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
9/12/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/13/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
9/14/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Grading
|
9/19/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Grading
|
9/21/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
9/21/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
9/26/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
9/28/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/29/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Pre-Inspection
|
10/4/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
10/5/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
10/13/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/16/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Grading
|
10/17/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
10/17/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Pre-Inspection
|
10/19/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/20/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
10/23/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Piling/Pier/Caisson
|
10/25/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/27/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Pre-Inspection
|
11/1/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
11/3/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Pre-Inspection
|
11/9/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
11/10/2023
|
Off-Hour Fees Due
|
|
|
Deputy Reinf. Concrete
|
11/13/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Pre-Inspection
|
11/17/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
11/20/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
11/22/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
11/22/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/28/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
12/7/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/8/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
12/19/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/20/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/28/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/29/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
ELECTRICAL-Rough
|
1/10/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
1/10/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
1/10/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/11/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
1/16/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/25/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
1/25/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
2/2/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
2/5/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
2/8/2024
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
2/9/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
3/4/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
3/11/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
3/12/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
3/14/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
4/18/2024
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
4/26/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/26/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/1/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/3/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Footing/Foundation/Slab
|
5/14/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/17/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
PLUMBING-Rough
|
5/24/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
6/3/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
6/4/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/6/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
6/12/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
6/12/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
6/13/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/13/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/17/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
7/3/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/5/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/8/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
7/9/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/10/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
7/31/2024
|
Approved
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/31/2024
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Wood Construction
|
8/1/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
9/11/2024
|
Not Ready for Inspection
|
STEPHANIE SWANSON
|
|
Deputy Drilled-In Anchors
|
9/12/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Drilled-In Anchors
|
9/13/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
9/13/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
9/17/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/19/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
10/8/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
10/24/2024
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
10/24/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/29/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
11/14/2024
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Pre-Inspection
|
11/15/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
11/15/2024
|
Partial Inspection
|
MICHAEL PELHAM
|
|
ELECTRICAL-Rough
|
12/4/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
12/9/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/13/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
12/16/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
12/16/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
12/16/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
12/16/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Gas Test
|
12/17/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
12/18/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
12/18/2024
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
12/18/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/19/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
12/23/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
12/23/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
12/23/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
12/23/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
1/8/2025
|
Partial Approval
|
BOBBY KEY
|
|
ELECTRICAL-Rough
|
1/13/2025
|
Approved
|
STEPHANIE SWANSON
|
|
PLUMBING-Rough
|
1/15/2025
|
Partial Approval
|
ARAM AVEDISIAN
|
|
BUILDING-Rough-Frame
|
1/17/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
1/17/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
1/17/2025
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
1/24/2025
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
1/24/2025
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
1/24/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
1/29/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
1/29/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
1/29/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
1/29/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
1/29/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
1/30/2025
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
1/31/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
3/12/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/12/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
3/12/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
3/24/2025
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/24/2025
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
3/24/2025
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
4/23/2025
|
Partial Approval
|
BOBBY KEY
|
|
Interior/Exterior Lathing
|
5/1/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
5/1/2025
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
5/19/2025
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
6/2/2025
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Drywall Nailing
|
6/9/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
6/10/2025
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
6/13/2025
|
Approved
|
SEAN HAUPT
|
|
Interior/Exterior Lathing
|
7/14/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Gas Test
|
8/15/2025
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/15/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
8/20/2025
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/20/2025
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Gas Test
|
8/22/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/22/2025
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
8/22/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
9/25/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
9/26/2025
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
5/12/2026
|
Approved
|
RYAN SALAZAR
|
|
PLUMBING-Final
|
5/13/2026
|
Conditional Approval
|
RYAN SALAZAR
|
|
ELECTRICAL-Final
|
5/14/2026
|
Partial Approval
|
RYAN SALAZAR
|
|
ELECTRICAL-Final
|
5/22/2026
|
Approved
|
RYAN SALAZAR
|