723 W 113TH ST 90044
Certificate Information: 723 W 113TH ST 90044
- Application / Permit
- 22010-10000-02424
- Plan Check / Job No.
- B22LA08870
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | ERIC WONG |
| Corrections Issued | 5/28/2022 | ERIC WONG |
| Quality Review Completed | 6/7/2022 | PETER KIM |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Applicant returned to address corrections | 1/19/2023 | ERIC WONG |
| Plan Check Approved | 1/26/2023 | ERIC WONG |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 6/6/2025 | BEN MOLSTAD |
| CofO Issued | 6/10/2025 | ANSON MAGLASANG |
| Permit Finaled | 6/10/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 6/29/2022 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 9/1/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 12/22/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/24/2023 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/5/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/20/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/3/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/25/2023 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 7/25/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/27/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 7/27/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/3/2023 | Partial Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/4/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 8/4/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 8/4/2023 | Approved | JAMES CHAVEZ |
| Insulation | 8/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Drywall Nailing | 8/14/2023 | Approved | JOHN KLARIN |
| Sewer | 9/26/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Underground Mechanical | 10/24/2023 | Partial Approval | JAMES CHAVEZ |
| Pre-Inspection | 12/7/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 1/30/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 7/3/2024 | Approved | JAMES CHAVEZ |
| Final | 7/3/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/3/2024 | Approved | JAMES CHAVEZ |
| Green Building Final | 7/3/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Final | 7/3/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 7/3/2024 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 7/3/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 7/3/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 7/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 7/9/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 7/9/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 7/9/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 7/25/2024 | Approved | JAMES CHAVEZ |
| Final | 7/25/2024 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 7/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Final | 7/25/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 7/25/2024 | Approved | JAMES CHAVEZ |
| Service/Power Release | 7/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 7/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 4/25/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Service/Power Release | 4/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 4/25/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 5/16/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 5/16/2025 | Approved | BEN MOLSTAD |
| Service/Power Release | 5/16/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 5/16/2025 | Approved | BEN MOLSTAD |
| Final | 6/4/2025 | No Access for Inspection | BEN MOLSTAD |
| Service/Power Release | 6/4/2025 | No Access for Inspection | BEN MOLSTAD |
| Final | 6/6/2025 | OK to Issue CofO | BEN MOLSTAD |
| Service/Power Release | 6/6/2025 | Approved | BEN MOLSTAD |