6075 W SELMA AVE 90028
Certificate Information: 6075 W SELMA AVE 90028
- Application / Permit
- 22010-10000-02406
- Plan Check / Job No.
- B22LA08823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU. (Addition 173 sf + Garage 353 sf = 526 S.F.) ADU PLAN CHECK PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 6/27/2022
- Issuing Office
- Current Status
- CofO Issued on 12/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | SUNMIN LEE |
| Corrections Issued | 5/20/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 6/9/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 6/13/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 6/21/2022 | SUNMIN LEE |
| Plan Check Approved | 6/22/2022 | SUNMIN LEE |
| Issued | 6/27/2022 | APPLICANT |
| CofO in Progress | 12/5/2022 | RUBEN SALAS |
| CofO Issued | 12/7/2022 | DEROLD HAUFF |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 5/25/2022 | MAX LODER |
| Address approval | Cleared | 5/27/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 5/27/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 5/27/2022 | JEANETTE VONG |
| "Q" conditions | Cleared | 6/6/2022 | ANACANY HURTADO |
| ZI | Cleared | 6/8/2022 | DAVID URITA |
Contact Information
| Architect | Kim,, Hoejun; Lic. No.: C37047 | 288 S. 2ND AVENUE, #B ARCADIA, CA 91006 |
| Contractor | Smart Construction And Plumbing; Lic. No.: 994517-B | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Zhang,, Zhiqiang; Lic. No.: M34617 | 410 S SAN GABRIEL BLVD #8 SAN GABRIEL, CA 91776 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2022 | Corrections Issued | JOSE AVILA |
| Deputy Drilled-In Anchors | 8/17/2022 | Conditional Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/22/2022 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/22/2022 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/30/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/7/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/7/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/13/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Gas Test | 9/13/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/13/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 9/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/20/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 9/27/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/27/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/7/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 10/7/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 10/7/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 10/13/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/13/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/13/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 10/20/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/20/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| Gas Test | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 11/8/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 11/21/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 11/21/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 11/21/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 12/5/2022 | OK to Issue CofO | RUBEN SALAS |