2665 N QUEEN ST 90039

Certificate Information: 2665 N QUEEN ST 90039

Application / Permit
22010-10000-02366
Plan Check / Job No.
B22LA08653
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert detached garage to ADU per GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/13/2022 RICARDO RAMIREZ
Corrections Issued 5/14/2022 RICARDO RAMIREZ
Applicant returned to address corrections 6/4/2022 RICARDO RAMIREZ
Applicant returned to address corrections 6/10/2022 RICARDO RAMIREZ
Plan Check Approved 6/28/2022 RICARDO RAMIREZ
Issued 7/14/2022 APPLICANT
CofO in Progress 12/14/2022 THOMAS LOGRASSO
Permit Finaled 12/24/2022 DEROLD HAUFF
CofO Issued 12/24/2022 DEROLD HAUFF
Permit Finaled 12/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/18/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/18/2022 JEANIE LAM
Sewer availability Cleared 5/18/2022 JEANIE LAM

Contact Information

Contractor Liebobuilders; Lic. No.: 1054050-B 18401 BURBANK BLVD SUITE 120      TARZANA, CA 91356
Engineer Asfour,, Andrew Victor; Lic. No.: NA87012       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 7/27/2022 Partial Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 7/29/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 7/29/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 7/29/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/3/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/3/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/5/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 8/12/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 8/12/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 8/17/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 8/17/2022 Approved THOMAS LOGRASSO
HVAC-Rough 8/17/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 8/17/2022 Approved THOMAS LOGRASSO
Insulation 8/24/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 8/24/2022 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 8/30/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Approved THOMAS LOGRASSO
HVAC-Rough 8/30/2022 Approved THOMAS LOGRASSO
Insulation 8/30/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/30/2022 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 9/21/2022 Approved THOMAS LOGRASSO
Sewer 9/21/2022 Approved THOMAS LOGRASSO
Underground Mechanical 9/21/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/31/2022 Conditional Approval THOMAS LOGRASSO
Final 10/31/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 10/31/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 10/31/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 10/31/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 12/2/2022 Approved THOMAS LOGRASSO
Final 12/2/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 12/2/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 12/13/2022 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 12/13/2022 Approved THOMAS LOGRASSO