719 N MARTEL AVE 90046

Certificate Information: 719 N MARTEL AVE 90046

Application / Permit
22010-10000-02357
Plan Check / Job No.
B22LA08649
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Conversion of existing recreation room into an ADU. All construction is existing and approved under permit numbers 1989WL81158 and 1989WL86096. This work is in response to a Code Violation Notice Case # 952494, Notice #A-5699077, dated April 07, 2022."COMPLY WITH DEPARTMENT ORDER effective date 04/07/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/10/2022
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/13/2022 MINA HABILI
Corrections Issued 5/16/2022 MINA HABILI
Applicant returned to address corrections 8/22/2022 ADAM HEGAZI
Plan Check Approved 8/30/2022 MINA HABILI
Issued 11/10/2022 APPLICANT
CofO in Progress 2/21/2025 RUBEN PEREZ
Permit Finaled 3/6/2025 DANIEL SANCHEZ
CofO Issued 3/6/2025 DANIEL SANCHEZ
Permit Finaled 3/6/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 6/1/2022 JEANETTE VONG
Sewer availability Cleared 6/1/2022 JEANETTE VONG
Construction within easement Cleared 7/23/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/12/2022 JEANETTE VONG

Contact Information

Architect Augustin,, Valery; Lic. No.: NA32614       ,
Contractor Owner-Builder       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2023 Not Ready for Inspection JOHN TCHANG
Pre-Inspection 12/18/2023 Approved ROBERT NILES
Pre-Inspection 4/26/2024 Approved PETER RUBIO
ELECTRICAL-Rough 6/12/2024 Corrections Issued ROBERT NILES
HVAC-Rough 6/12/2024 Corrections Issued ROBERT NILES
PLUMBING-Rough 6/12/2024 Corrections Issued ROBERT NILES
ELECTRICAL-Rough 6/14/2024 Partial Inspection RUBEN PEREZ
HVAC-Rough 6/14/2024 Approved RUBEN PEREZ
Insulation 6/14/2024 Approved RUBEN PEREZ
ELECTRICAL-Final 8/20/2024 Corrections Issued ROBERT NILES
Final 8/20/2024 Not Ready for Inspection ROBERT NILES
HVAC-Final 8/20/2024 Approved ROBERT NILES
METHANE-Final 8/20/2024 Corrections Issued ROBERT NILES
PLUMBING-Final 8/20/2024 Corrections Issued ROBERT NILES
Smoke Detectors 8/20/2024 Approved ROBERT NILES
ELECTRICAL-Final 12/4/2024 Approved PETER RUBIO
Final 12/4/2024 OK to Issue CofO PETER RUBIO
METHANE-Final 12/4/2024 Approved PETER RUBIO
PLUMBING-Final 12/4/2024 Approved PETER RUBIO