15251 W EL CASCO ST 91342

Certificate Information: 15251 W EL CASCO ST 91342

Application / Permit
22010-10000-02345
Plan Check / Job No.
B22LA08603
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 6/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2022 APPLICANT
Assigned to Plan Check Engineer 5/10/2022 JOSEPH RAFOLS
Corrections Issued 5/10/2022 JOSEPH RAFOLS
Building Plans Picked Up 5/11/2022 APPLICANT
Plan Check Approved 6/16/2022 SHANGQIN XIE
Issued 6/23/2022 APPLICANT
CofO in Progress 6/1/2023 ARAM AVEDISIAN
Permit Finaled 8/23/2023 RUBEN SALAS
CofO Issued 8/23/2023 RUBEN SALAS
Permit Finaled 8/23/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/13/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 5/16/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/16/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 5/19/2022 KIRK LINKLATER
Low Impact Development Cleared 6/15/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 6/15/2022 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 6/16/2022 JOSEPH RAFOLS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/26/2022 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 11/1/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/15/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 11/15/2022 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 11/15/2022 Partial Approval ARAM AVEDISIAN
Insulation 11/21/2022 Partial Approval JORDAN KUTZLY
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/8/2022 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 1/24/2023 Not Ready for Inspection ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 1/24/2023 Approved ARAM AVEDISIAN
Wood Frame 1/24/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 1/31/2023 Approved ARAM AVEDISIAN
Green Building Rough 1/31/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/31/2023 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 1/31/2023 Approved ARAM AVEDISIAN
Insulation 2/3/2023 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 2/7/2023 Approved ARAM AVEDISIAN
Insulation 2/7/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/15/2023 Partial Approval ARAM AVEDISIAN
Gas Test 3/15/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/15/2023 Partial Approval ARAM AVEDISIAN
Sewer 3/15/2023 Corrections Issued ARAM AVEDISIAN
Final 3/16/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/16/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/16/2023 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 3/16/2023 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 3/16/2023 Approved ARAM AVEDISIAN
Final 5/15/2023 Corrections Issued ARAM AVEDISIAN
Service/Power Release 5/15/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 6/1/2023 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 6/1/2023 Approved ARAM AVEDISIAN