15251 W EL CASCO ST 91342
Certificate Information: 15251 W EL CASCO ST 91342
- Application / Permit
- 22010-10000-02345
- Plan Check / Job No.
- B22LA08603
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2022 | JOSEPH RAFOLS |
| Corrections Issued | 5/10/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| Plan Check Approved | 6/16/2022 | SHANGQIN XIE |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 6/1/2023 | ARAM AVEDISIAN |
| Permit Finaled | 8/23/2023 | RUBEN SALAS |
| CofO Issued | 8/23/2023 | RUBEN SALAS |
| Permit Finaled | 8/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 5/16/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 5/19/2022 | KIRK LINKLATER |
| Low Impact Development | Cleared | 6/15/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | JOSE DUARTE-DIAZ |
| GPI Written Notices | Cleared | 6/16/2022 | JOSEPH RAFOLS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/26/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/15/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/15/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 11/21/2022 | Partial Approval | JORDAN KUTZLY |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/8/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 1/24/2023 | Approved | ARAM AVEDISIAN |
| Wood Frame | 1/24/2023 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/31/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/31/2023 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 1/31/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 2/3/2023 | Conditional Approval | ARAM AVEDISIAN |
| Drywall Nailing | 2/7/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 2/7/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 3/15/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 3/15/2023 | Corrections Issued | ARAM AVEDISIAN |
| Final | 3/16/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/16/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 3/16/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 3/16/2023 | Approved | ARAM AVEDISIAN |
| Final | 5/15/2023 | Corrections Issued | ARAM AVEDISIAN |
| Service/Power Release | 5/15/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 6/1/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 6/1/2023 | Approved | ARAM AVEDISIAN |