17950 W RAYMER ST 91325
Certificate Information: 17950 W RAYMER ST 91325
- Application / Permit
- 22010-10000-02319
- Plan Check / Job No.
- B22LA08494
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ACCESSORY DWELLING UNIT PER CA G.C. 65852.2(e)(1)(B) and applicable part 2 of LAMC 12.22 A.33(c)-(d), (g) . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy"
- Permit Issued
- Issued on 12/13/2022
- Issuing Office
- Current Status
- Issued on 12/13/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2022 | FERNANDO FLORES |
| Corrections Issued | 5/10/2022 | FERNANDO FLORES |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Applicant returned to address corrections | 12/7/2022 | GEORGE ALVAREZ |
| Issued | 12/13/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/18/2022 | ROMAN GUTIERREZ |
| ZA Case | Cleared | 6/1/2022 | RUBEN VASQUEZ |
| Metro Rail approval | Cleared | 8/10/2022 | FERNANDO FLORES |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/11/2022 | ROMAN GUTIERREZ |
Contact Information
| No Data Available. |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/7/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/21/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/24/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/24/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 6/22/2023 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/12/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/3/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 8/3/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 8/23/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/5/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/11/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 10/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/18/2023 | Corrections Issued | JAVIER RAMOS JR |
| Sewer | 10/20/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 10/20/2023 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 10/26/2023 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 11/1/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 11/1/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 11/1/2023 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/1/2023 | Corrections Issued | JAVIER RAMOS JR |
| Drywall Nailing | 11/8/2023 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 8/27/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 8/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 8/27/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Final | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Final | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Service/Power Release | 10/21/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/10/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/10/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/10/2024 | Approved | JAVIER RAMOS JR |
| Final | 12/10/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 12/10/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 12/10/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 12/10/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/10/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/10/2024 | Approved | JAVIER RAMOS JR |
| Final | 12/16/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Gas Test | 12/16/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 12/16/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/16/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 12/18/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 12/18/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/18/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 1/29/2025 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 1/29/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 3/7/2025 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 3/7/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 3/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 3/26/2025 | Approved | CHRISTOPHER ROJAS |