17950 W RAYMER ST 91325

Certificate Information: 17950 W RAYMER ST 91325

Application / Permit
22010-10000-02319
Plan Check / Job No.
B22LA08494
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNIT PER CA G.C. 65852.2(e)(1)(B) and applicable part 2 of LAMC 12.22 A.33(c)-(d), (g) . WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy"
Permit Issued
Issued on 12/13/2022
Issuing Office
Current Status
Issued on 12/13/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/9/2022 FERNANDO FLORES
Corrections Issued 5/10/2022 FERNANDO FLORES
Building Plans Picked Up 5/12/2022 APPLICANT
Applicant returned to address corrections 12/7/2022 GEORGE ALVAREZ
Issued 12/13/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/17/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/18/2022 ROMAN GUTIERREZ
ZA Case Cleared 6/1/2022 RUBEN VASQUEZ
Metro Rail approval Cleared 8/10/2022 FERNANDO FLORES
Eng Process Fee Ord 176,300 Cleared 8/11/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 8/11/2022 ROMAN GUTIERREZ

Contact Information

No Data Available.

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/7/2023 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 4/17/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/21/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 5/24/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 5/24/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/22/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 7/12/2023 Not Ready for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 8/3/2023 Partial Approval JACK KARGODORIAN
Shower Pan 8/3/2023 Not Ready for Inspection JACK KARGODORIAN
Shower Pan 8/23/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/5/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/11/2023 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 10/18/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 10/18/2023 Corrections Issued JAVIER RAMOS JR
Sewer 10/20/2023 Approved JAVIER RAMOS JR
Underground Mechanical 10/20/2023 Partial Approval JAVIER RAMOS JR
HVAC-Rough 10/26/2023 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Approved JAVIER RAMOS JR
Green Building Rough 11/1/2023 Approved JAVIER RAMOS JR
HVAC-Rough 11/1/2023 Not Ready for Inspection JAVIER RAMOS JR
Insulation 11/1/2023 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 11/1/2023 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 11/8/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/27/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 8/27/2024 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 8/27/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 10/21/2024 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 12/10/2024 Approved JAVIER RAMOS JR
Drywall Nailing 12/10/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/10/2024 Approved JAVIER RAMOS JR
Final 12/10/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 12/10/2024 Approved JAVIER RAMOS JR
HVAC-Final 12/10/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 12/10/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 12/10/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 12/10/2024 Approved JAVIER RAMOS JR
Final 12/16/2024 Not Ready for Inspection JAVIER RAMOS JR
Gas Test 12/16/2024 Approved JAVIER RAMOS JR
HVAC-Final 12/16/2024 Approved JAVIER RAMOS JR
Service/Power Release 12/16/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 12/18/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 12/18/2024 Approved JAVIER RAMOS JR
Service/Power Release 12/18/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 1/29/2025 Corrections Issued JAVIER RAMOS JR
Service/Power Release 1/29/2025 Not Ready for Inspection JAVIER RAMOS JR
Final 3/7/2025 Corrections Issued JAVIER RAMOS JR
Service/Power Release 3/7/2025 Not Ready for Inspection JAVIER RAMOS JR
Final 3/14/2025 Corrections Issued JAVIER RAMOS JR
Service/Power Release 3/26/2025 Approved CHRISTOPHER ROJAS