744 N WILTON PL 90038
Certificate Information: 744 N WILTON PL 90038
- Application / Permit
- 22010-10000-02307
- Plan Check / Job No.
- B22LA08437
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 10/20/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | STARR CHEN |
| Corrections Issued | 5/24/2022 | STARR CHEN |
| Quality Review Completed | 5/26/2022 | KEN GILL |
| Building Plans Picked Up | 5/27/2022 | APPLICANT |
| Applicant returned to address corrections | 9/6/2023 | STARR CHEN |
| Applicant returned to address corrections | 9/20/2023 | STARR CHEN |
| Plan Check Approved | 10/19/2023 | STARR CHEN |
| Issued | 10/20/2023 | APPLICANT |
| CofO in Progress | 10/29/2025 | JEFFREY MEAD |
| Permit Finaled | 11/10/2025 | DEROLD HAUFF |
| CofO Issued | 11/10/2025 | DEROLD HAUFF |
| Permit Finaled | 11/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | CINDY QI |
| Sewer availability | Cleared | 6/6/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 7/27/2022 | KURT CORRAL |
| Construction near power lines | Cleared | 12/15/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/28/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 8/10/2023 | BIJAN ZADEH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/14/2023 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 11/17/2023 | Conditional Approval | JEFFREY MEAD |
| PLUMBING-Rough | 12/8/2023 | Partial Approval | JEFFREY MEAD |
| Insulation | 12/12/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 12/12/2023 | Partial Approval | JEFFREY MEAD |
| Wood Frame | 12/12/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Conditional Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 3/27/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/27/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/27/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 4/2/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 4/2/2024 | Approved | JEFFREY MEAD |
| Underground Mechanical | 4/2/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/23/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 4/23/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 4/23/2024 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/16/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 5/16/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 5/16/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/20/2024 | Corrections Issued | JEFFREY MEAD |
| Deputy Wood Construction | 5/20/2024 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/20/2024 | Approved | JEFFREY MEAD |
| Green Building Final | 5/20/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 5/20/2024 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 5/20/2024 | Approved | JEFFREY MEAD |
| Insulation | 5/24/2024 | Partial Approval | JEFFREY MEAD |
| Drywall Nailing | 5/30/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/14/2024 | Approved | JEFFREY MEAD |
| Drywall Nailing | 6/14/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/14/2024 | Approved | JEFFREY MEAD |
| Shower Pan | 6/14/2024 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/1/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 10/7/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 10/7/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 10/7/2024 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 2/20/2025 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 2/20/2025 | Corrections Issued | JEFFREY MEAD |
| Service/Power Release | 2/20/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 4/11/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/11/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 4/11/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 4/11/2025 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 5/15/2025 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 8/4/2025 | Approved | JEFFREY MEAD |
| Final | 8/4/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 8/4/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/4/2025 | Approved | JEFFREY MEAD |
| Service/Power Release | 8/4/2025 | Approved | JEFFREY MEAD |
| Final | 8/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 8/12/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 9/25/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 10/7/2025 | Corrections Issued | JEFFREY MEAD |
| Final | 10/28/2025 | OK to Issue CofO | JEFFREY MEAD |