3114 S COLBY AVE 90066
Certificate Information: 3114 S COLBY AVE 90066
- Application / Permit
- 22010-10000-02301
- Plan Check / Job No.
- B22LA08413
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ROOF DECK PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 10/1/2023
- Issuing Office
- Current Status
- Issued on 10/1/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | KEVIN MORALES |
| Corrections Issued | 5/26/2022 | KEVIN MORALES |
| Quality Review Completed | 6/1/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/3/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 10/7/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 10/20/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 1/25/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 3/29/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 4/7/2023 | KEVIN MORALES |
| Plan Check Approved | 4/24/2023 | KEVIN MORALES |
| Issued | 10/1/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2022 | AMAAN MALIK |
| Specific Plan | Cleared | 10/24/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 1/24/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/26/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/31/2023 | JEANIE LAM |
| GPI Written Notices | Cleared | 4/6/2023 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 4/6/2023 | KEVIN MORALES |
| Construction near power lines | Cleared | 4/13/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Dlk Construction Inc; Lic. No.: 961510-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 12/18/2023 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 12/18/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Partial Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Partial Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 1/18/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/23/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Corrections Issued | JESUS PINEDA |
| Deputy Drilled-In Anchors | 1/26/2024 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 2/2/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 2/2/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 2/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 2/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/16/2024 | Approved | STEPHANIE SWANSON |
| Sewer | 2/16/2024 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 2/16/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/28/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 2/28/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 2/28/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/28/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 2/29/2024 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 2/29/2024 | Approved | JESUS PINEDA |
| Insulation | 3/13/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/14/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 3/27/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 8/20/2024 | Approved | JESUS PINEDA |
| Final | 8/20/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/20/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/20/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/20/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 8/20/2024 | Not Required | JESUS PINEDA |
| Smoke Detectors | 8/20/2024 | Approved | JESUS PINEDA |
| Final | 8/23/2024 | Partial Approval | DANIEL VERA |
| Gas Test | 8/23/2024 | Approved | DANIEL VERA |
| Green Building Final | 8/23/2024 | Approved | DANIEL VERA |
| Final | 8/26/2024 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 7/25/2025 | Not Ready for Inspection | MICHAEL PELHAM |