822 W 115TH ST 90044

Certificate Information: 822 W 115TH ST 90044

Application / Permit
22010-10000-02282
Plan Check / Job No.
B22LA08368
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: BUILDING A NEW NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ''THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY''
Permit Issued
Issued on 11/21/2022
Issuing Office
Current Status
Issued on 11/21/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 SERGIO GUTIERREZ
Corrections Issued 6/8/2022 SERGIO GUTIERREZ
Quality Review Completed 6/8/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/5/2022 SERGIO GUTIERREZ
Plan Check Approved 11/8/2022 SERGIO GUTIERREZ
Issued 11/21/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/4/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 8/16/2022 ELAINE LEI
Sewer availability Cleared 8/16/2022 ELAINE LEI
Roof/Waste drainage to street Cleared 8/25/2022 CINDY QI
Hydrant and Access approval Cleared 9/18/2022 JOHN CONNEALLY

Contact Information

Contractor Vertexbeta Inc; Lic. No.: 1094438-B       ,
Engineer Herrera,, Edgar E; Lic. No.: C67603 1929 GREENLEAF DR      WEST COVINA, CA 91792

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/24/2023 Not Ready for Inspection JAMES CHAVEZ
Posting Pre-Inspection 1/26/2023 Approved JOHN KLARIN
Sewer 2/8/2023 Corrections Issued JAMES CHAVEZ
Sewer 9/25/2023 Corrections Issued JAMES CHAVEZ
Underground Mechanical 9/27/2023 Partial Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 10/16/2023 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 10/19/2023 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/4/2023 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/8/2023 Approved JOHN KLARIN
Sewer 12/8/2023 Partial Approval JOHN KLARIN