400 N ARNO WAY 90272
Certificate Information: 400 N ARNO WAY 90272
- Application / Permit
- 22010-10000-02241
- Plan Check / Job No.
- B22LA08245
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33 (c)-(d) 2 OF 4
- Permit Issued
- Issued on 2/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/21/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 5/26/2022 | KEN GILL |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Applicant returned to address corrections | 10/14/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 2/10/2023 | ADRIANA LOPEZ |
| Issued | 2/10/2023 | APPLICANT |
| CofO in Progress | 2/24/2026 | MEL KHACHATOURIAN |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
| CofO Issued | 2/24/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2022 | CATHERINE ADROVER |
| Permit | Cleared | 8/18/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/22/2022 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 11/30/2022 | MAXFIELD VERMY |
| Coastal Zone | Cleared | 11/30/2022 | MAXFIELD VERMY |
| Coastal Zone | Cleared | 11/30/2022 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 12/19/2022 | LAVEON RIDER |
| Trees in Parkway | Cleared | 1/12/2023 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 1/17/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 1/17/2023 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 1/23/2023 | JASON NG |
| GPI Written Notices | Cleared | 2/7/2023 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 2/7/2023 | ADRIANA LOPEZ |
Contact Information
| Architect | Bakhoum,, Nagy R; Lic. No.: C26503 | 3800 PACIFIC COAST HIGHWAY TORRANCE, CA 90505 |
| Contractor | T Apple General Contracting Incorporated; Lic. No.: 1064015-B | 760 N TOWNE AVE CLAREMONT, CA 91711 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: C58475 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2023 | Partial Approval | BRENDAN LOONEY |
| Reinforced Concrete Frame | 5/11/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 5/11/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/22/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 8/9/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 11/30/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 11/30/2023 | Approved | EVAN COOPER |
| HVAC-Rough | 12/1/2023 | Corrections Issued | EVAN COOPER |
| Shower Pan | 12/6/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 12/12/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | EVAN COOPER |
| Green Building Rough | 12/13/2023 | Approved | EVAN COOPER |
| Insulation | 12/13/2023 | Corrections Issued | EVAN COOPER |
| Verify Sprinkler Sign Off | 12/13/2023 | Approved | EVAN COOPER |
| Insulation | 12/22/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 1/8/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 1/22/2024 | Approved | EVAN COOPER |
| Underground Mechanical | 6/21/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/26/2024 | Approved | EVAN COOPER |
| HVAC-Final | 12/27/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/30/2024 | Approved | EVAN COOPER |
| Final | 12/30/2024 | Corrections Issued | EVAN COOPER |
| Final | 8/19/2025 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 8/19/2025 | Approved | BOBBY KEY |
| Green Building Final | 8/19/2025 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/19/2025 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 8/19/2025 | Not Required | BOBBY KEY |
| Smoke Detectors | 8/19/2025 | Approved | BOBBY KEY |
| Final | 12/5/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 2/23/2026 | OK to Issue CofO | MEL KHACHATOURIAN |
| Service/Power Release | 2/23/2026 | Approved | MEL KHACHATOURIAN |