3944 S DENKER AVE 90062

Certificate Information: 3944 S DENKER AVE 90062

Application / Permit
22010-10000-02212
Plan Check / Job No.
B22LA08134
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached ADU per LAMC 12.22 A.33(c) and (d) all work per WFPP
Permit Issued
Issued on 5/17/2023
Issuing Office
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 5/25/2022 LUKE GONZALES
Corrections Issued 5/26/2022 LUKE GONZALES
Applicant returned to address corrections 4/5/2023 LUKE GONZALES
Plan Check Approved 5/17/2023 JOSEPH RAFOLS
Issued 5/17/2023 APPLICANT
CofO in Progress 6/9/2024 SABAS ALONSO
Permit Finaled 6/11/2024 DEROLD HAUFF
CofO Issued 6/11/2024 DEROLD HAUFF
Permit Finaled 6/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/30/2022 JEANIE LAM
Construction near power lines Cleared 8/23/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/28/2022 JEANIE LAM
Sewer availability Cleared 9/28/2022 JEANIE LAM
Low Impact Development Cleared 3/31/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 4/3/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2023 Corrections Issued STUART CHAPMAN
Underground Mechanical 7/17/2023 Approved STUART CHAPMAN
Footing/Foundation/Slab 7/21/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 8/10/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved SABAS ALONSO
PLUMBING-Rough 8/10/2023 Approved SABAS ALONSO
Sewer 8/10/2023 Approved SABAS ALONSO
Underground Mechanical 8/10/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/25/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 8/25/2023 Approved SABAS ALONSO
Green Building Rough 8/25/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 8/25/2023 Partial Approval SABAS ALONSO
Insulation 8/31/2023 No Access for Inspection SABAS ALONSO
Shower Pan 8/31/2023 No Access for Inspection SABAS ALONSO
Insulation 9/11/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 9/11/2023 Approved MICHAEL LEWIS
Shower Pan 9/11/2023 Approved MICHAEL LEWIS
Insulation 9/14/2023 Approved SABAS ALONSO
Drywall Nailing 9/22/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/29/2023 Approved SABAS ALONSO
ELECTRICAL-Final 12/29/2023 Not Ready for Inspection SABAS ALONSO
Final 12/29/2023 Corrections Issued SABAS ALONSO
Green Building Final 12/29/2023 Approved SABAS ALONSO
HVAC-Final 12/29/2023 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 12/29/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/29/2023 SGSOV Approved SABAS ALONSO
Service/Power Release 12/29/2023 Approved SABAS ALONSO
Smoke Detectors 12/29/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/29/2023 Approved SABAS ALONSO
ELECTRICAL-Final 1/16/2024 Approved SABAS ALONSO
Final 1/16/2024 Corrections Issued SABAS ALONSO
Service/Power Release 1/16/2024 Not Ready for Inspection SABAS ALONSO
Final 2/7/2024 Corrections Issued SABAS ALONSO
Service/Power Release 2/7/2024 Not Ready for Inspection SABAS ALONSO
Final 3/11/2024 Corrections Issued SABAS ALONSO
Service/Power Release 3/11/2024 Approved SABAS ALONSO
ELECTRICAL-Final 5/8/2024 Approved SABAS ALONSO
Final 5/8/2024 Not Ready for Inspection SABAS ALONSO
Service/Power Release 5/8/2024 Not Ready for Inspection SABAS ALONSO
Final 5/20/2024 Not Ready for Inspection SABAS ALONSO
Service/Power Release 5/20/2024 Approved SABAS ALONSO
Final 6/7/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 6/7/2024 Approved SABAS ALONSO