3625 1/2 S HUGHES AVE 90034
Certificate Information: 3625 1/2 S HUGHES AVE 90034
- Application / Permit
- 22010-10000-02208
- Plan Check / Job No.
- B22LA08133
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan, NEW DETACHED ADU per state law
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2022 | MINA HABILI |
| Corrections Issued | 5/12/2022 | MINA HABILI |
| Applicant returned to address corrections | 6/18/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/20/2022 | MINA HABILI |
| Plan Check Approved | 9/28/2022 | JOSEPH RAFOLS |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | CLAYTON GRAHAM |
| Permit Finaled | 6/9/2023 | DANIEL ORRANTE |
| CofO Issued | 6/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/1/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2022 | JENSON LEE |
| Sewer availability | Cleared | 6/22/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 7/5/2022 | KIRK LINKLATER |
| Address approval | Cleared | 7/6/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 7/6/2022 | JENSON LEE |
| Specific Plan | Cleared | 8/8/2022 | JAZMIN ROQUE |
| Construction near power lines | Cleared | 9/15/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/15/2022 | RIDWAN HARDY |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Gabor Design Group Inc The; Lic. No.: 842370-B | 4587 DON FELIPE DR LOS ANGELES, CA 90008 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/15/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 1/12/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| MERV13>=Rough | 1/12/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/12/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 1/12/2023 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 1/12/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/18/2023 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 1/18/2023 | Approved | DAVID FEILER |
| Green Building Rough | 1/18/2023 | Approved | DAVID FEILER |
| HVAC-Rough | 1/18/2023 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 1/18/2023 | Approved | DAVID FEILER |
| PLUMBING-Rough | 1/18/2023 | Approved | DAVID FEILER |
| Sewer | 1/18/2023 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | DAVID FEILER |
| HVAC-Rough | 1/24/2023 | Approved | DAVID FEILER |
| Insulation | 1/24/2023 | Approved | DAVID FEILER |
| MERV13>=Rough | 1/24/2023 | Approved | DAVID FEILER |
| Drywall Nailing | 1/31/2023 | Approved | JULIAN AMAYA |
| ELECTRICAL-Final | 4/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 4/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 4/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 4/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 4/21/2023 | Approved | CLAYTON GRAHAM |
| Smoke Detectors | 4/21/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Deputy Wood Construction | 5/1/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| MERV13>=Final | 5/10/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 5/10/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Not Ready | CLAYTON GRAHAM |
| Service/Power Release | 5/10/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 5/10/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 5/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 5/18/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 6/8/2023 | Approved | CLAYTON GRAHAM |
| Final | 6/8/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| Green Building Final | 6/8/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 6/8/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 6/8/2023 | Approved | CLAYTON GRAHAM |