11350 W CASHMERE ST 90049
Certificate Information: 11350 W CASHMERE ST 90049
- Application / Permit
- 22010-10000-02193
- Plan Check / Job No.
- B22LA08075
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU STATE APPROVED FACTORY BUILT HOUSING PER GCS CA Govt. Code 65852.2(e)(1)(D). FOUNDATION PER ENGINEERS DESIGN.
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Current Status
- CofO Issued on 5/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | ALBERT SERVIN |
| Corrections Issued | 5/23/2022 | ALBERT SERVIN |
| Quality Review Completed | 5/26/2022 | KEN GILL |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Plan Check Approved | 12/1/2022 | ALBERT SERVIN |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 5/4/2023 | CARLOS MATAMOROS |
| Permit Finaled | 5/15/2023 | DANIEL ORRANTE |
| CofO Issued | 5/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/30/2022 | SUNG JOON WON |
| Address approval | Cleared | 7/1/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2022 | JENSON LEE |
| Sewer availability | Cleared | 7/7/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 7/12/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 7/17/2022 | RUEL COLE |
| Specific Plan | Cleared | 7/25/2022 | ROBERT SANCHEZ |
| Construction near power lines | Cleared | 9/7/2022 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 11/29/2022 | ALBERT SERVIN |
Contact Information
| Contractor | Cover Building Technologies; Lic. No.: 1039029-B | 1415 W 178TH ST GARDENA, CA 90248 |
| Engineer | Nielsen,, Gregory Michael Wat; Lic. No.: S6653 | 4991 WESTPARK DR NORTH HOLLYWOOD, CA 91601 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/18/2023 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 2/23/2023 | Approved | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/3/2023 | Conditional Approval | CARLOS MATAMOROS |
| Sewer | 3/8/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 3/8/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Rough | 5/3/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Barrier | 5/3/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Final | 5/3/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Rough | 5/3/2023 | Approved | CARLOS MATAMOROS |
| METHANE-Subgrade | 5/3/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Service/Power Release | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Smoke Detectors | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 5/3/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/4/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/4/2023 | Approved | CARLOS MATAMOROS |
| Final | 5/4/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/4/2023 | Approved | CARLOS MATAMOROS |
| Green Building Final | 5/4/2023 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 5/4/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 5/4/2023 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 5/4/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 5/4/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 5/4/2023 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 5/4/2023 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 5/4/2023 | Approved | CARLOS MATAMOROS |