1607 E ROBIDOUX ST 90744
Certificate Information: 1607 E ROBIDOUX ST 90744
- Application / Permit
- 22010-10000-02169
- Plan Check / Job No.
- B22LA08024
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE (2-STORY)
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | CARLOS MONTES |
| Corrections Issued | 5/18/2022 | CARLOS MONTES |
| Quality Review Completed | 5/26/2022 | KEN GILL |
| Building Plans Picked Up | 5/27/2022 | APPLICANT |
| Plan Check Approved | 2/16/2023 | CARLOS MONTES |
| Issued | 2/17/2023 | APPLICANT |
| CofO in Progress | 12/8/2023 | EUGENE CASSIDY |
| Permit Finaled | 12/14/2023 | DONALD CRICHLOW |
| CofO Issued | 12/14/2023 | DONALD CRICHLOW |
| Permit Finaled | 12/14/2023 | DONALD CRICHLOW |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/16/2022 | AMMAR ELTAWIL |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 8/17/2022 | HUGO LOPEZ |
| Hydrant and Access approval | Cleared | 9/23/2022 | LAVEON RIDER |
| Abandoned oil well | Cleared | 10/11/2022 | LAVEON RIDER |
| Clean Up Green Up | Cleared | 11/16/2022 | MAXFIELD VERMY |
| Address approval | Cleared | 11/22/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | ERIK BEASLEY |
| Permit | Cleared | 11/30/2022 | ERIK BEASLEY |
| Trees in Parkway | Cleared | 1/24/2023 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/21/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/28/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/28/2023 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 4/28/2023 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 4/28/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/11/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 5/11/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 5/11/2023 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 5/22/2023 | Corrections Issued | EUGENE CASSIDY |
| Deputy Wood Construction | 5/23/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/5/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/5/2023 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/5/2023 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 6/5/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 6/8/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/8/2023 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 6/8/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/8/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 6/8/2023 | Approved | EUGENE CASSIDY |
| Wood Frame | 6/8/2023 | Approved | EUGENE CASSIDY |
| Insulation | 6/13/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 6/21/2023 | Approved | EUGENE CASSIDY |
| Sewer | 8/22/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/29/2023 | Approved | EUGENE CASSIDY |
| Sewer | 8/29/2023 | Approved | EUGENE CASSIDY |
| Final | 10/18/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/18/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 10/18/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/18/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/31/2023 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/31/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/31/2023 | Approved | EUGENE CASSIDY |
| Final | 11/30/2023 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 11/30/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/7/2023 | Approved | EUGENE CASSIDY |
| Final | 12/7/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 12/7/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/7/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 12/7/2023 | Approved | EUGENE CASSIDY |