|
Pre-Inspection
|
12/31/2024
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
1/23/2025
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
1/24/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
1/24/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
2/10/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/11/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/27/2025
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
2/27/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
2/28/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/3/2025
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
3/3/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/4/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/10/2025
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
3/10/2025
|
Approved
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
3/12/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/24/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/27/2025
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
3/27/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
4/3/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
4/4/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/15/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
4/16/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/28/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
5/20/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2025
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Wood Construction
|
6/4/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/6/2025
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
6/6/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/6/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
6/6/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
7/16/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/14/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
8/14/2025
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
9/8/2025
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
9/8/2025
|
Approved
|
JAMES POWERS
|
|
Deputy Wood Construction
|
9/10/2025
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/11/2025
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/11/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/11/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Drilled-In Anchors
|
9/15/2025
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
10/9/2025
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/14/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
10/15/2025
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2025
|
Partial Approval
|
JAMES POWERS
|
|
Special/Order Compliance
|
11/6/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Deputy Drilled-In Anchors
|
11/18/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
11/18/2025
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
12/15/2025
|
Approved
|
JAMES POWERS
|
|
Deputy Wood Construction
|
12/31/2025
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
12/31/2025
|
Approved
|
JAMES POWERS
|
|
Pre-Inspection
|
2/4/2026
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Drywall Nailing
|
2/11/2026
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Drywall Nailing
|
2/23/2026
|
Partial Approval
|
ALFREDO LOPEZ
|
|
Drywall Nailing
|
3/18/2026
|
Partial Approval
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
3/18/2026
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
3/25/2026
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
3/25/2026
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/1/2026
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/6/2026
|
Partial Approval
|
PAUL BAZERKANIAN
|
|
Interior/Exterior Lathing
|
4/6/2026
|
Partial Approval
|
PAUL BAZERKANIAN
|
|
Drywall Nailing
|
4/16/2026
|
Partial Approval
|
RAFAEL ESPINOZA
|