4408 1/2 W FINLEY AVE 90027

Certificate Information: 4408 1/2 W FINLEY AVE 90027

Application / Permit
22010-10000-02157
Plan Check / Job No.
B22LA07954
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 3-CAR GARAGE INTO AN ACCESSORY DWELING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/5/2022
Issuing Office
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 ZAW HAN
Corrections Issued 5/5/2022 MONICA RAMIREZ
Plan Check Approved 9/4/2022 ZAW HAN
Issued 9/5/2022 APPLICANT
CofO in Progress 7/31/2023 SCOTT FINNILA
Permit Finaled 7/31/2023 RONALD MYRICK
CofO Issued 7/31/2023 RONALD MYRICK
Permit Finaled 7/31/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 7/25/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 7/25/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 7/25/2022 JEANETTE VONG
Sewer availability Cleared 7/25/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/28/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 7/29/2022 RICARDO BOHORQUEZ
Construction near power lines Cleared 8/18/2022 RIDWAN HARDY
Permit Cleared 8/19/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: NA4808       ,

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2022 Corrections Issued JOSEPH MCGARRY
Wood Frame 10/12/2022 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 10/17/2022 Conditional Approval JOSEPH MCGARRY
PLUMBING-Rough 11/1/2022 Partial Approval JOSEPH MCGARRY
Sewer 11/1/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 12/22/2022 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Conditional Approval JOSEPH MCGARRY
Green Building Rough 12/22/2022 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 12/22/2022 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 12/22/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 1/19/2023 Conditional Approval JOSEPH MCGARRY
Gas Test 1/19/2023 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 1/19/2023 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Rough 1/19/2023 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 2/3/2023 Conditional Approval JOSEPH MCGARRY
Green Building Rough 2/3/2023 Approved JOSEPH MCGARRY
HVAC-Rough 2/3/2023 Partial Approval JOSEPH MCGARRY
Insulation 2/3/2023 Approved JOSEPH MCGARRY
Gas Test 2/9/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 2/9/2023 Approved JEFFREY MEAD
Drywall Nailing 3/9/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/9/2023 Approved JOSEPH MCGARRY
Shower Pan 3/9/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/9/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Final 5/9/2023 Approved JOSEPH MCGARRY
Final 5/9/2023 Corrections Issued JOSEPH MCGARRY
Green Building Final 5/9/2023 Approved JOSEPH MCGARRY
HVAC-Final 5/9/2023 Approved JOSEPH MCGARRY
PLUMBING-Final 5/9/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 5/9/2023 Approved JOSEPH MCGARRY
Final 7/31/2023 OK to Issue CofO SCOTT FINNILA