1302 3/4 W 35TH ST 90007

Certificate Information: 1302 3/4 W 35TH ST 90007

Application / Permit
22010-10000-02156
Plan Check / Job No.
B22LA07953
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(eplan) NEW 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d).
Permit Issued
Issued on 7/14/2023
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 YOUNG KIM
Corrections Issued 6/2/2022 YOUNG KIM
Quality Review Completed 6/10/2022 FARUK SEZER
Applicant returned to address corrections 6/16/2022 YOUNG KIM
Applicant returned to address corrections 12/16/2022 YOUNG KIM
Applicant returned to address corrections 1/25/2023 YOUNG KIM
Plan Check Approved 1/27/2023 YOUNG KIM
Issued 7/14/2023 APPLICANT
CofO in Progress 10/1/2024 SABAS ALONSO
CofO Issued 10/3/2024 RUBEN SALAS
Permit Finaled 10/3/2024 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 8/23/2022 JASON CHAN
Address approval Cleared 10/20/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 10/20/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/26/2022 WALLIE JONG
Sewer availability Cleared 10/26/2022 WALLIE JONG
Low Impact Development Cleared 12/2/2022 DEBORA LEITE

Contact Information

Architect , ; Lic. No.: C37928 3131 FOOTHILL BLVD.   SUITE L    LA CRESCENTA, CA 91214
Contractor Bloomfield Construction Inc; Lic. No.: 1091558-B       ,
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 9/11/2023 Conditional Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/11/2023 Partial Approval SABAS ALONSO
METHANE-Subgrade 9/11/2023 Approved SABAS ALONSO
Sewer 9/11/2023 Approved SABAS ALONSO
Underground Mechanical 9/11/2023 Partial Approval SABAS ALONSO
Deputy Methane Barrier 9/13/2023 Conditional Approval SABAS ALONSO
METHANE-Barrier 9/15/2023 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/18/2023 Approved SABAS ALONSO
Underground Mechanical 9/18/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 9/21/2023 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 9/26/2023 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/14/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 11/14/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 11/15/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/14/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/14/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Corrections Issued SABAS ALONSO
Green Building Rough 12/14/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 12/14/2023 Approved SABAS ALONSO
METHANE-Rough 12/14/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 12/14/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/14/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 1/2/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 1/3/2024 Conditional Approval SABAS ALONSO
Green Building Rough 1/3/2024 Approved SABAS ALONSO
Insulation 1/3/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/3/2024 Partial Approval SABAS ALONSO
METHANE-Rough 1/3/2024 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 1/10/2024 Approved SABAS ALONSO
Shower Pan 1/16/2024 Approved SABAS ALONSO
Pre-Inspection 4/2/2024 Partial Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/26/2024 Approved SABAS ALONSO
Final 4/26/2024 Corrections Issued SABAS ALONSO
Green Building Final 4/26/2024 Corrections Issued SABAS ALONSO
METHANE-Final 4/26/2024 Approved SABAS ALONSO
METHANE-Rough 4/26/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 4/26/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 4/26/2024 Approved SABAS ALONSO
Final 7/19/2024 Not Ready for Inspection SABAS ALONSO
Green Building Final 7/19/2024 Approved SABAS ALONSO
Final 9/17/2024 Corrections Issued SABAS ALONSO
Final 9/26/2024 OK to Issue CofO SABAS ALONSO