1433 1/2 W 253RD ST 90710
Certificate Information: 1433 1/2 W 253RD ST 90710
- Application / Permit
- 22010-10000-02155
- Plan Check / Job No.
- B22LA07951
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 1-STORY DETACHED ADU (1200 SF) PER LAMC 12.22A.33(c)-(d).
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2022 | VIVIAN LAO |
| Corrections Issued | 5/31/2022 | VIVIAN LAO |
| Quality Review Completed | 6/8/2022 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/19/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 11/14/2022 | VIVIAN LAO |
| Plan Check Approved | 11/29/2022 | VIVIAN LAO |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 6/14/2024 | EUGENE CASSIDY |
| Permit Finaled | 6/24/2024 | ANSON MAGLASANG |
| CofO Issued | 6/24/2024 | ANSON MAGLASANG |
| Permit Finaled | 6/24/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/3/2022 | ERIK BEASLEY |
| Low Impact Development | Cleared | 11/10/2022 | CHRIS VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/21/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/22/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Breezy Builders Inc; Lic. No.: 1072775-B | 121 MAYFAIR IRVINE, CA 92620 |
| Engineer | Jalalpour,, Mohammad; Lic. No.: NA6696 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/18/2023 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 6/1/2023 | Partial Approval | EUGENE CASSIDY |
| Deputy Methane Barrier | 6/6/2023 | Partial Approval | EUGENE CASSIDY |
| Deputy Methane Barrier | 6/20/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/21/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 6/21/2023 | Partial Approval | EUGENE CASSIDY |
| METHANE-Subgrade | 6/21/2023 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/27/2023 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 7/3/2023 | Approved | EUGENE CASSIDY |
| Service/Power Release | 7/19/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 8/22/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Deputy Methane Barrier | 8/25/2023 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 9/22/2023 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 9/22/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/27/2023 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 9/27/2023 | Approved | EUGENE CASSIDY |
| Insulation | 10/11/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 10/17/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 10/17/2023 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 11/6/2023 | Approved | EUGENE CASSIDY |
| Sewer | 2/16/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 3/5/2024 | Approved | EUGENE CASSIDY |
| Final | 3/21/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/21/2024 | Approved | EUGENE CASSIDY |
| Green Building Final | 3/21/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 3/21/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 3/21/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 3/21/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 3/21/2024 | Approved | EUGENE CASSIDY |
| Final | 6/11/2024 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 6/11/2024 | Approved | EUGENE CASSIDY |
| Service/Power Release | 6/11/2024 | Not Required | EUGENE CASSIDY |