2201 S BUNDY DR 90064
Certificate Information: 2201 S BUNDY DR 90064
- Application / Permit
- 22010-10000-02128
- Plan Check / Job No.
- B22LA07872
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 8 STORY 136 UNITS (11% ELI = 15) AFFORDABLE HOUSING APARTMENT, LIVE-WORK, AND CAFE (CORE AND SHELL) TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT/CAFE OVER 2 LEVEL SUBTERRANEAN PARKING, TIER 4 TOC WITH ADDITIONAL INCENTIVE
- Permit Issued
- Issued on 2/27/2026
- Issuing Office
- Metro
- Current Status
- Issued on 2/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | KEVIN MORALES |
| Corrections Issued | 5/17/2022 | KEVIN MORALES |
| Quality Review Completed | 5/23/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/23/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 9/8/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 9/9/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 12/20/2022 | KEVIN MORALES |
| Plan Check Approved | 2/27/2026 | KEVIN MORALES |
| Issued | 2/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2023 | DINAH GARIN |
| Highway dedication | Cleared | 11/16/2023 | DINAH GARIN |
| Green Code | Cleared | 1/10/2024 | KEVIN MORALES |
| Hydrant and Access approval | Cleared | 6/10/2024 | LAVEON RIDER |
| Low Impact Development | Cleared | 9/25/2024 | MARTIN FRAGOSO |
| ZA Case | Cleared | 10/9/2024 | YINGSHI HUANG |
| Fire Marshal Fire Life Safety | Cleared | 10/11/2024 | WILLIAM JOHNS |
| Density Bonus 12.22.A.31 | Cleared | 10/17/2024 | ASHLEY MEDINA |
| SB8 RUD | Cleared | 10/17/2024 | ASHLEY MEDINA |
| Specific Plan | Cleared | 10/27/2024 | PEDRO AYALA |
| Specific Plan | Cleared | 10/27/2024 | PEDRO AYALA |
| Work Adjacent to Public Way | Cleared | 2/25/2025 | LARRY LEE |
| Building over 36-ft | Cleared | 3/5/2025 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 3/14/2025 | ELIZABETH TOMS |
| Metro Rail approval | Cleared | 3/27/2025 | JENNIFER SU |
| Roof/Waste drainage to street | Cleared | 4/2/2025 | DIANA RENTERIA |
| Excavation more than 5-ft deep | Cleared | 4/17/2025 | CALOSHA APPROVED |
| Sewer availability | Cleared | 7/9/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 1/15/2026 | JULISSA LOPEZ-HODOYAN |
| Frnt yard landscape/Water mgmt | Cleared | 2/26/2026 | FIPE LEILUA |
| Miscellaneous | Cleared | 2/26/2026 | FIPE LEILUA |
| Miscellaneous | Cleared | 2/26/2026 | FIPE LEILUA |
| Opn space landscape/Water mgmt | Cleared | 2/26/2026 | FIPE LEILUA |
| Site Plan review | Cleared | 2/26/2026 | FIPE LEILUA |
| ZI | Cleared | 2/26/2026 | FIPE LEILUA |
| Specific Plan | Cleared | 2/27/2026 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Architect | Loh,, Radziah M; Lic. No.: C29367 | 7411 TERRACE DRIVE EL CERRITO, CA 94530 |
| Contractor | Carmel Construction West Llc; Lic. No.: 1070377-B | 1000 SANSOME STREET 1ST FLOOR SAN FRANCISCO, CA 94111 |
| Engineer | Aden,, Mark; Lic. No.: S4779 | 1224 W. RIVERSIDE AVE., #208 SPOKANE, WA 99201 |
Inspector Information
| DANIEL VARNUM, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 3/23/2026 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 3/23/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 3/24/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 3/25/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 3/26/2026 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 3/26/2026 | Partial Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 3/27/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 3/31/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/1/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/2/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/3/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/7/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 4/7/2026 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 4/7/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Wood Construction | 4/8/2026 | Approved | DANIEL VARNUM |
| Deputy Wood Construction | 4/9/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/10/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/13/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/14/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/15/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/16/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/17/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 4/17/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 4/17/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/20/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/21/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 4/21/2026 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 4/21/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/22/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/23/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/24/2026 | Conditional Approval | PAUL DAVIDSON |
| Insulation | 4/24/2026 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 4/24/2026 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 4/27/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/28/2026 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/29/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/30/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/1/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/4/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/4/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2026 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 5/4/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Wood Construction | 5/5/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/6/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/6/2026 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 5/6/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/7/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/7/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 5/7/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Wood Construction | 5/8/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 5/11/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/11/2026 | Partial Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 5/11/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/12/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/13/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/14/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/14/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 5/14/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Wood Construction | 5/15/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/18/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/19/2026 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 5/19/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/20/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/20/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 5/20/2026 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 5/20/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/21/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/21/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 5/21/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Wood Construction | 5/22/2026 | Conditional Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 5/26/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/26/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Insulation | 5/26/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 5/26/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/27/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/28/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/28/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 5/28/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/29/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 6/1/2026 | Conditional Approval | DANIEL ARMENTA |
| Deputy Wood Construction | 6/2/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 6/3/2026 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 6/3/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2026 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 6/3/2026 | Partial Approval | DANIEL VARNUM |
| Deputy Wood Construction | 6/4/2026 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 6/5/2026 | Conditional Approval | PAUL DAVIDSON |