6406 N RIVERTON AVE 91606

Certificate Information: 6406 N RIVERTON AVE 91606

Application / Permit
22010-10000-02102
Plan Check / Job No.
B22LA07738
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD IN FRONT
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
CofO Issued on 2/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 JAD BASMA
Corrections Issued 5/14/2022 JAD BASMA
Quality Review Completed 5/20/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 5/26/2022 APPLICANT
Applicant returned to address corrections 8/19/2022 JAD BASMA
Applicant returned to address corrections 5/17/2023 JAD BASMA
Plan Check Approved 6/21/2023 JAD BASMA
Issued 8/11/2023 APPLICANT
CofO in Progress 1/17/2025 JOSE AVILA
Permit Finaled 2/19/2025 RUBEN SALAS
CofO Issued 2/19/2025 RUBEN SALAS
Permit Finaled 2/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/19/2022 CARLOS AGUILERA
Address approval Cleared 5/19/2022 CARLOS AGUILERA
Highway dedication Cleared 5/19/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 6/22/2022 KURT CORRAL
Frnt yard landscape/Water mgmt Cleared 6/23/2022 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 3/28/2023 ROMAN GUTIERREZ
Sewer availability Cleared 3/28/2023 ROMAN GUTIERREZ
Low Impact Development Cleared 5/8/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/22/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Aqx, Engineering; Lic. No.: S5289 1520 BROOKHOLLOW   SUITE 45    SANTA ANA, CA 92705

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/4/2024 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/8/2024 Partial Approval JOHN HAYES
Underground Mechanical 1/8/2024 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/12/2024 Approved JOHN HAYES
Underground Mechanical 1/19/2024 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Corrections Issued CRAIG DAVIS
Deputy Wood Construction 2/14/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Corrections Issued JOHN HAYES
Wood Frame 4/12/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/16/2024 Partial Approval JOHN HAYES
Wood Frame 4/16/2024 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Corrections Issued JOHN HAYES
PLUMBING-Rough 4/18/2024 Partial Approval JOHN HAYES
Wood Frame 4/18/2024 Not Ready for Inspection JOHN HAYES
Shower Pan 5/2/2024 Approved JOSE AVILA
HVAC-Rough 5/20/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 5/30/2024 Approved JOSE AVILA
ELECTRICAL-Rough 5/30/2024 Approved JOSE AVILA
Verify Sprinkler Sign Off 5/30/2024 Approved JOSE AVILA
Interior/Exterior Lathing 6/4/2024 Not Ready for Inspection JOSE AVILA
Insulation 6/10/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 6/10/2024 Corrections Issued JOSE AVILA
Insulation 6/20/2024 Not Ready for Inspection JOSE AVILA
Insulation 6/27/2024 Partial Approval JOSE AVILA
Insulation 7/2/2024 Approved JOSE AVILA
Drywall Nailing 7/9/2024 Approved JOSE AVILA
Underground Mechanical 9/3/2024 Partial Approval JOSE AVILA
Underground Mechanical 9/5/2024 Approved JOSE AVILA
Gas Test 10/29/2024 Approved JOSE AVILA
PLUMBING-Final 10/29/2024 Corrections Issued JOSE AVILA
HVAC-Final 11/20/2024 Approved JOSE AVILA
PLUMBING-Final 11/22/2024 Approved JOSE AVILA
ELECTRICAL-Final 12/13/2024 Approved JOSE AVILA
Final 1/13/2025 OK to Issue CofO JOSE AVILA
Footing/Foundation/Slab 1/13/2025 Approved JOSE AVILA
Green Building Final 1/13/2025 Approved JOSE AVILA
Green Building Rough 1/13/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/13/2025 SGSOV Approved JOSE AVILA
Service/Power Release 1/13/2025 Approved JOSE AVILA
Smoke Detectors 1/13/2025 Approved JOSE AVILA