6406 N RIVERTON AVE 91606
Certificate Information: 6406 N RIVERTON AVE 91606
- Application / Permit
- 22010-10000-02102
- Plan Check / Job No.
- B22LA07738
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD IN FRONT
- Permit Issued
- Issued on 8/11/2023
- Issuing Office
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | JAD BASMA |
| Corrections Issued | 5/14/2022 | JAD BASMA |
| Quality Review Completed | 5/20/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Applicant returned to address corrections | 8/19/2022 | JAD BASMA |
| Applicant returned to address corrections | 5/17/2023 | JAD BASMA |
| Plan Check Approved | 6/21/2023 | JAD BASMA |
| Issued | 8/11/2023 | APPLICANT |
| CofO in Progress | 1/17/2025 | JOSE AVILA |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
| CofO Issued | 2/19/2025 | RUBEN SALAS |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Address approval | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Highway dedication | Cleared | 5/19/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 6/22/2022 | KURT CORRAL |
| Frnt yard landscape/Water mgmt | Cleared | 6/23/2022 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 3/28/2023 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 5/8/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/22/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aqx, Engineering; Lic. No.: S5289 | 1520 BROOKHOLLOW SUITE 45 SANTA ANA, CA 92705 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/4/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/8/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 1/8/2024 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/12/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 1/19/2024 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Corrections Issued | CRAIG DAVIS |
| Deputy Wood Construction | 2/14/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Corrections Issued | JOHN HAYES |
| Wood Frame | 4/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 4/16/2024 | Partial Approval | JOHN HAYES |
| Wood Frame | 4/16/2024 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 4/18/2024 | Partial Approval | JOHN HAYES |
| Wood Frame | 4/18/2024 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 5/2/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 5/20/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 5/30/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 5/30/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 6/4/2024 | Not Ready for Inspection | JOSE AVILA |
| Insulation | 6/10/2024 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 6/10/2024 | Corrections Issued | JOSE AVILA |
| Insulation | 6/20/2024 | Not Ready for Inspection | JOSE AVILA |
| Insulation | 6/27/2024 | Partial Approval | JOSE AVILA |
| Insulation | 7/2/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 7/9/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 9/3/2024 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 9/5/2024 | Approved | JOSE AVILA |
| Gas Test | 10/29/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 10/29/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 11/20/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 11/22/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/13/2024 | Approved | JOSE AVILA |
| Final | 1/13/2025 | OK to Issue CofO | JOSE AVILA |
| Footing/Foundation/Slab | 1/13/2025 | Approved | JOSE AVILA |
| Green Building Final | 1/13/2025 | Approved | JOSE AVILA |
| Green Building Rough | 1/13/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 1/13/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 1/13/2025 | Approved | JOSE AVILA |