1114-1116 W LOWEN ST 90744
Certificate Information: 1114-1116 W LOWEN ST 90744
- Application / Permit
- 22010-10000-02090
- Plan Check / Job No.
- B22LA07713
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY DWELLING WITH ACCESSORY DWELLING UNIT. See comment. 1 OF 2
- Permit Issued
- Issued on 11/19/2025
- Issuing Office
- Metro
- Current Status
- Issued on 11/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | TSE MING HUANG |
| Corrections Issued | 6/9/2022 | TSE MING HUANG |
| Quality Review Completed | 6/15/2022 | KEN GILL |
| Applicant returned to address corrections | 11/2/2022 | TSE MING HUANG |
| Building Plans Picked Up | 11/9/2022 | APPLICANT |
| Applicant returned to address corrections | 11/22/2022 | TSE MING HUANG |
| Plan Check Approved | 12/30/2022 | TSE MING HUANG |
| Plan Check Approved | 5/22/2025 | TSE MING HUANG |
| Issued | 11/19/2025 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 8/26/2022 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/26/2022 | RUBEN VASQUEZ |
| Address approval | Cleared | 8/29/2022 | HUGO LOPEZ |
| Permit | Cleared | 8/29/2022 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 8/31/2022 | HUGO LOPEZ |
| Low Impact Development | Cleared | 9/28/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/2/2022 | HUGO LOPEZ |
| Abandoned oil well | Cleared | 12/8/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/12/2026 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 3/12/2026 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 3/12/2026 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 3/19/2026 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 3/19/2026 | Partial Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2026 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/30/2026 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/30/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/1/2026 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 5/1/2026 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 5/1/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/1/2026 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 5/1/2026 | Approved | EUGENE CASSIDY |
| Insulation | 5/7/2026 | Conditional Approval | BEN MOLSTAD |
| Drywall Nailing | 5/14/2026 | Conditional Approval | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/14/2026 | Conditional Approval | EUGENE CASSIDY |
| Sewer | 7/20/2026 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 7/20/2026 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 7/23/2026 | Approved | BEN MOLSTAD |
| Underground Mechanical | 7/23/2026 | Approved | BEN MOLSTAD |