17633 W LOS ALIMOS ST 91344
Certificate Information: 17633 W LOS ALIMOS ST 91344
- Application / Permit
- 22010-10000-02069
- Plan Check / Job No.
- B22LA07655
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SB9 UNIT (1510 SQFT). 1 OF 2
- Permit Issued
- Issued on 11/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/27/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 6/3/2022 | KEN GILL |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Plan Check Approved | 11/17/2022 | ADRIANA LOPEZ |
| Issued | 11/22/2022 | APPLICANT |
| CofO in Progress | 11/20/2023 | DAVID SCANTLIN |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
| CofO Issued | 12/27/2023 | JOHN JANSON |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/2/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/13/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Senate Bill 9 | Cleared | 9/22/2022 | NELSON RODRIGUEZ |
| ZI | Cleared | 9/22/2022 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 10/24/2022 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 12/28/2022 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 1/27/2023 | Corrections Issued | STEVEN BACK |
| Special/Order Compliance | 1/27/2023 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 1/31/2023 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 2/2/2023 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 2/2/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 5/1/2023 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 5/1/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/1/2023 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 5/1/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/8/2023 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 5/8/2023 | Approved | STEVEN BACK |
| Insulation | 5/8/2023 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 5/8/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/12/2023 | Approved | STEVEN BACK |
| Drywall Nailing | 5/12/2023 | Approved | STEVEN BACK |
| Shower Pan | 6/6/2023 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/13/2023 | Approved | STEVEN BACK |
| Shower Pan | 6/13/2023 | Approved | STEVEN BACK |
| Underground Mechanical | 8/2/2023 | Approved | JEFFREY BULL |
| Final | 10/30/2023 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/30/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 10/30/2023 | Not Ready for Inspection | STEVEN BACK |
| Final | 11/17/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Smoke Detectors | 11/17/2023 | Approved | DAVID SCANTLIN |