16100 W MULHOLLAND DR 90049
Certificate Information: 16100 W MULHOLLAND DR 90049
- Application / Permit
- 22010-10000-02058
- Plan Check / Job No.
- B22LA07568
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- (N) 1 story storage/trash building. NFPA-13 sprinkler thru-out. See comments
- Permit Issued
- Issued on 7/6/2023
- Issuing Office
- Current Status
- CofO Corrected on 11/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2022 | HERNAN ARREOLA |
| Corrections Issued | 5/23/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 5/25/2022 | SAI KHUM |
| Applicant returned to address corrections | 1/16/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/16/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/23/2023 | HERNAN ARREOLA |
| Plan Check Approved | 6/30/2023 | HERNAN ARREOLA |
| Issued | 7/6/2023 | APPLICANT |
| CofO Issued-Status Void | 11/21/2024 | DAVID TSAU |
| Permit Finaled-Status Void | 11/21/2024 | DAVID TSAU |
| Re-Activate Permit | 11/27/2024 | DAVID TSAU |
| Permit Finaled | 11/27/2024 | DAVID TSAU |
| CofO Corrected | 11/27/2024 | DAVID TSAU |
| Permit Finaled | 11/27/2024 | DAVID TSAU |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/2/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/2/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/2/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/2/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 6/2/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 6/6/2022 | KURT CORRAL |
| CPC | Cleared | 6/15/2022 | JASON CHAN |
| Miscellaneous | Cleared | 6/15/2022 | JASON CHAN |
| Specific Plan | Cleared | 6/15/2022 | JASON CHAN |
| ZA Case | Cleared | 6/15/2022 | JASON CHAN |
| Green Code | Cleared | 12/20/2022 | AARON COSTA |
| Low Impact Development | Cleared | 12/20/2022 | MARTIN FRAGOSO |
| DAS Clearance | Cleared | 12/21/2022 | MICHAEL LOPEZ |
| Roof/Waste drainage to street | Cleared | 12/31/2022 | SAUL GARCIA |
| GPI Written Notices | Cleared | 1/17/2023 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 1/17/2023 | CHARLES POWELL |
| Sewer availability | Cleared | 1/19/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Del Amo Construction Inc; Lic. No.: 744458-B | 23840 MADISON STREET TORRANCE, CA 90505 |
| Engineer | Sabol,, Thomas Andrew; Lic. No.: S3175 | 888 S FIGUEROA ST 18TH FL LOS ANGELES, CA 90017 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Grading | 7/26/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/27/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 9/19/2023 | Approved | DERRICK SPENCER |
| Masonry Wall/Backfill | 9/27/2023 | Partial Approval | DERRICK SPENCER |
| Wall Anchors | 9/27/2023 | Approved | DERRICK SPENCER |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | GRANT WOODS |
| Verify Sprinkler Sign Off | 10/17/2023 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 10/17/2023 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 10/27/2023 | Partial Approval | GRANT WOODS |
| Green Building Rough | 10/27/2023 | Not Ready for Inspection | GRANT WOODS |
| Special/Order Compliance | 10/27/2023 | Conditional Approval | CASIMIR BRITTON |
| Drywall Nailing | 11/2/2023 | Partial Approval | GRANT WOODS |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | GRANT WOODS |
| Insulation | 11/2/2023 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 11/2/2023 | Conditional Approval | CASIMIR BRITTON |
| Verify Sprinkler Sign Off | 11/2/2023 | Approved | GRANT WOODS |
| Wood Frame | 11/2/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 11/8/2023 | Partial Approval | FARHAD DADBIN |
| Green Building Rough | 11/8/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 11/29/2023 | Partial Approval | GRANT WOODS |
| Wall Anchors | 11/29/2023 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 12/27/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 5/15/2024 | Approved | DERRICK SPENCER |
| Final | 5/15/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 5/15/2024 | Approved | DERRICK SPENCER |
| Green Building Rough | 5/15/2024 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 5/15/2024 | Approved | DERRICK SPENCER |
| Wood Frame | 5/15/2024 | Approved | DERRICK SPENCER |
| Final | 5/30/2024 | Conditional Approval | GRANT WOODS |
| Final | 8/29/2024 | Off-Hour Fees Due | |
| Final | 8/30/2024 | Conditional Approval | GRANT WOODS |