5319 E HYDE ST 90032

Certificate Information: 5319 E HYDE ST 90032

Application / Permit
22010-10000-02056
Plan Check / Job No.
B22LA07556
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2 STORY ADU W/ PORCH AND TERRACE. ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/7/2023
Issuing Office
Metro
Current Status
Issued on 12/7/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 ADRIANA LOPEZ
Corrections Issued 5/21/2022 ADRIANA LOPEZ
Quality Review Completed 5/26/2022 KEN GILL
Building Plans Picked Up 2/24/2023 APPLICANT
Plan Check Approved 10/3/2023 ADRIANA LOPEZ
Issued 12/7/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/7/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 6/10/2023 KEVIN AVILA
Sewer availability Cleared 6/10/2023 KEVIN AVILA
Hydrant and Access approval Cleared 9/12/2023 MATTHEW CRAIG
Low Impact Development Cleared 9/12/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/28/2023 AMBER CAMPBELL
GPI Written Notices Cleared 10/3/2023 ADRIANA LOPEZ
Grading Pre-Inspection Cleared 10/3/2023 ADRIANA LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/19/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 12/19/2023 Conditional Approval AMY COLIN
Grounding or Bonding 12/19/2023 Partial Inspection AMY COLIN
PLUMBING-Rough 12/19/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 1/2/2024 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval AMY COLIN
Footing/Foundation/Slab 1/16/2024 Partial Approval AMY COLIN
Footing/Foundation/Slab 2/15/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Corrections Issued JOAQUIN GREENOUGH
Deputy Wood Construction 3/22/2024 Conditional Approval LILIANA PORTILLO
Deputy Wood Construction 3/29/2024 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 4/2/2024 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Approved LILIANA PORTILLO
Gas Test 5/24/2024 Approved LILIANA PORTILLO
Underground Mechanical 5/24/2024 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 6/5/2024 Approved LILIANA PORTILLO
HVAC-Rough 6/5/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 6/5/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/7/2024 Corrections Issued LILIANA PORTILLO
Gas Test 6/7/2024 Approved LILIANA PORTILLO
Green Building Rough 6/7/2024 Approved LILIANA PORTILLO
HVAC-Rough 6/7/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/7/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 6/7/2024 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 6/7/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/17/2024 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 6/26/2024 Corrections Issued LILIANA PORTILLO
Insulation 6/26/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
Drywall Nailing 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
Pre-Inspection 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 6/12/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 7/15/2025 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 8/22/2025 Approved LILIANA PORTILLO
Drywall Nailing 8/22/2025 Approved LILIANA PORTILLO
Final 8/22/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 8/22/2025 Approved LILIANA PORTILLO
Green Building Final 8/22/2025 Not Ready for Inspection LILIANA PORTILLO
Insulation 8/22/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 8/22/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 8/22/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Not Ready BRENDAN MORELLI
Pre-Inspection 11/3/2025 Partial Inspection LILIANA PORTILLO
Final 12/18/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 12/18/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 12/18/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/18/2025 Approved LILIANA PORTILLO
Final 12/30/2025 Not Ready for Inspection JOSH MEISTER
Green Building Final 12/30/2025 Not Ready for Inspection JOSH MEISTER
Service/Power Release 12/30/2025 Not Ready for Inspection JOSH MEISTER
Final 1/16/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 1/16/2026 Approved LILIANA PORTILLO
Service/Power Release 1/16/2026 Approved LILIANA PORTILLO
Final 1/22/2026 Not Ready for Inspection LILIANA PORTILLO