5319 E HYDE ST 90032
Certificate Information: 5319 E HYDE ST 90032
- Application / Permit
- 22010-10000-02056
- Plan Check / Job No.
- B22LA07556
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2 STORY ADU W/ PORCH AND TERRACE. ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 12/7/2023
- Issuing Office
- Metro
- Current Status
- Issued on 12/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | ADRIANA LOPEZ |
| Corrections Issued | 5/21/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 5/26/2022 | KEN GILL |
| Building Plans Picked Up | 2/24/2023 | APPLICANT |
| Plan Check Approved | 10/3/2023 | ADRIANA LOPEZ |
| Issued | 12/7/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2023 | KEVIN AVILA |
| Sewer availability | Cleared | 6/10/2023 | KEVIN AVILA |
| Hydrant and Access approval | Cleared | 9/12/2023 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/12/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/28/2023 | AMBER CAMPBELL |
| GPI Written Notices | Cleared | 10/3/2023 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 10/3/2023 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/19/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 12/19/2023 | Conditional Approval | AMY COLIN |
| Grounding or Bonding | 12/19/2023 | Partial Inspection | AMY COLIN |
| PLUMBING-Rough | 12/19/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 1/2/2024 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 1/16/2024 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 2/15/2024 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 3/22/2024 | Conditional Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 3/29/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 4/2/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2024 | Approved | LILIANA PORTILLO |
| Gas Test | 5/24/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/24/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 6/5/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 6/5/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 6/5/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/7/2024 | Corrections Issued | LILIANA PORTILLO |
| Gas Test | 6/7/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 6/7/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 6/7/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/7/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 6/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 6/7/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/17/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 6/26/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Pre-Inspection | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 6/12/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 7/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/22/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/22/2025 | Approved | LILIANA PORTILLO |
| Final | 8/22/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/22/2025 | Approved | LILIANA PORTILLO |
| Green Building Final | 8/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 8/22/2025 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 8/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 8/22/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Pre-Inspection | 11/3/2025 | Partial Inspection | LILIANA PORTILLO |
| Final | 12/18/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 12/18/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 12/18/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 12/18/2025 | Approved | LILIANA PORTILLO |
| Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| Service/Power Release | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| Final | 1/16/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/16/2026 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/16/2026 | Approved | LILIANA PORTILLO |
| Final | 1/22/2026 | Not Ready for Inspection | LILIANA PORTILLO |