705 W 82ND ST 90044
Certificate Information: 705 W 82ND ST 90044
- Application / Permit
- 22010-10000-02039
- Plan Check / Job No.
- B22LA07457
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT AT REAR OF EXISTING DUPLEX (ADU-B) (ADU A UNDER SEPARATE PERMIT)
- Permit Issued
- Issued on 12/23/2022
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | CARLOS MONTES |
| Plan Check Approved | 12/22/2022 | PRANITA SHAH |
| Issued | 12/23/2022 | APPLICANT |
| CofO in Progress | 5/23/2024 | MICHAEL LEWIS |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
| CofO Issued | 5/29/2024 | DEROLD HAUFF |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/23/2022 | LONDY ALVARADO |
| Address approval | Cleared | 9/27/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 10/4/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 10/26/2022 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 11/18/2022 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: NA92143 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/13/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/15/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/7/2023 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/28/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/8/2023 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 5/8/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 5/8/2023 | Corrections Issued | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 5/8/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/15/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/15/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/19/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/6/2023 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 6/6/2023 | Approved | STUART CHAPMAN |
| Insulation | 6/15/2023 | Conditional Approval | MICHAEL LEWIS |
| Drywall Nailing | 6/28/2023 | Corrections Issued | MICHAEL LEWIS |
| Insulation | 6/28/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/13/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 10/2/2023 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Not Required | MICHAEL LEWIS |
| Service/Power Release | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Service/Power Release | 10/12/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 3/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/2/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 4/2/2024 | Partial Inspection | MICHAEL LEWIS |
| Smoke Detectors | 4/2/2024 | Approved | MICHAEL LEWIS |
| Final | 4/8/2024 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 5/21/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 5/21/2024 | Approved | MICHAEL LEWIS |