705 1/2 W 82ND ST 90044

Certificate Information: 705 1/2 W 82ND ST 90044

Application / Permit
22010-10000-02038
Plan Check / Job No.
B22LA08447
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan . New detached Accessory dwelling unit on the rear (ADU-A) per CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 12/23/2022
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 MONICA RAMIREZ
Corrections Issued 6/10/2022 MONICA RAMIREZ
Quality Review Completed 6/14/2022 RODOLFO ARIAS
Applicant returned to address corrections 11/7/2022 MONICA RAMIREZ
Applicant returned to address corrections 12/21/2022 MONICA RAMIREZ
Plan Check Approved 12/22/2022 MONICA RAMIREZ
Issued 12/23/2022 APPLICANT
CofO in Progress 5/23/2024 MICHAEL LEWIS
Permit Finaled 5/29/2024 DEROLD HAUFF
CofO Issued 5/29/2024 DEROLD HAUFF
Permit Finaled 5/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/27/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/27/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/27/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 8/20/2022 RUEL COLE
Tenant Habitability Plan Cleared 8/23/2022 MICHAEL SOTO
Construction near power lines Cleared 9/7/2022 RIDWAN HARDY
Low Impact Development Cleared 9/20/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 9/23/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/13/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 2/15/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 3/2/2023 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/7/2023 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/13/2023 Not Ready for Inspection LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 3/28/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 3/28/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 5/8/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval MICHAEL LEWIS
HVAC-Rough 5/8/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 5/8/2023 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 5/8/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 5/15/2023 Approved MICHAEL LEWIS
HVAC-Rough 5/15/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/15/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 5/15/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/19/2023 Corrections Issued MICHAEL LEWIS
Green Building Rough 5/19/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 6/6/2023 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 6/6/2023 Approved STUART CHAPMAN
Insulation 6/15/2023 Conditional Approval MICHAEL LEWIS
Drywall Nailing 6/28/2023 Corrections Issued MICHAEL LEWIS
Insulation 6/28/2023 Approved MICHAEL LEWIS
Drywall Nailing 7/13/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 10/2/2023 Corrections Issued MICHAEL LEWIS
Final 10/2/2023 Partial Inspection MICHAEL LEWIS
Green Building Final 10/2/2023 Corrections Issued MICHAEL LEWIS
HVAC-Final 10/2/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 10/2/2023 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Not Required MICHAEL LEWIS
Service/Power Release 10/2/2023 Corrections Issued MICHAEL LEWIS
Smoke Detectors 10/2/2023 Corrections Issued MICHAEL LEWIS
Service/Power Release 10/12/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/2/2024 Approved MICHAEL LEWIS
PLUMBING-Final 4/2/2024 Partial Inspection MICHAEL LEWIS
Smoke Detectors 4/2/2024 Approved MICHAEL LEWIS
Final 4/8/2024 Partial Inspection MICHAEL LEWIS
Green Building Final 4/8/2024 Corrections Issued MICHAEL LEWIS
HVAC-Final 4/8/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 4/8/2024 Corrections Issued MICHAEL LEWIS
Final 5/21/2024 OK to Issue CofO MICHAEL LEWIS
Green Building Final 5/21/2024 Approved MICHAEL LEWIS