2115 S WALNUT AVE 90291
Certificate Information: 2115 S WALNUT AVE 90291
- Application / Permit
- 22010-10000-01995
- Plan Check / Job No.
- B22LA07187
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING. 1 OF 2
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | TSE MING HUANG |
| Corrections Issued | 6/8/2022 | TSE MING HUANG |
| Quality Review Completed | 6/15/2022 | KEN GILL |
| Building Plans Picked Up | 6/30/2022 | APPLICANT |
| Plan Check Approved | 2/10/2023 | TSE MING HUANG |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 3/9/2026 | ANTHONY EGSON |
| Permit Finaled | 3/26/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/26/2026 | RICHARD STEINBACH |
| CofO Issued | 3/26/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 8/1/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 8/9/2022 | VALERIA CEJA |
| Hydrant and Access approval | Cleared | 11/1/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 1/5/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/10/2023 | CATHERINE ADROVER |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Rimon Construction Inc; Lic. No.: 1077839-B | 554 S SAN VICENTE BLVD STE 206 LOS ANGELES, CA 90046 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/4/2024 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 6/4/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 6/6/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 6/11/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 6/18/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 8/20/2024 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/23/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/23/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 8/28/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 8/30/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 8/30/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Conditional Approval | HERBERT GIRON |
| Green Building Rough | 9/27/2024 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 9/27/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/11/2024 | Partial Approval | DAVID FEILER |
| Green Building Rough | 10/11/2024 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 10/11/2024 | Corrections Issued | DAVID FEILER |
| Wood Frame | 10/11/2024 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 10/16/2024 | Conditional Approval | HERBERT GIRON |
| Final | 10/16/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 10/16/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/16/2024 | Partial Approval | HERBERT GIRON |
| Insulation | 10/22/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/28/2024 | Approved | HERBERT GIRON |
| Gas Test | 10/28/2024 | Corrections Issued | HERBERT GIRON |
| Gas Test | 11/1/2024 | Not Ready for Inspection | DAVID FEILER |
| Shower Pan | 11/1/2024 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/6/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/21/2025 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/4/2025 | Approved | JESUS RODRIGUEZ |
| Final | 2/25/2026 | Not Ready for Inspection | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Not Ready | RUBEN RIVAS |
| Service/Power Release | 2/25/2026 | Corrections Issued | RUBEN RIVAS |
| Smoke Detectors | 2/25/2026 | No Access for Inspection | RUBEN RIVAS |
| Final | 3/6/2026 | OK to Issue CofO | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 3/6/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 3/6/2026 | Approved | ANTHONY EGSON |