3412 1/2 E 7TH ST 90023

Certificate Information: 3412 1/2 E 7TH ST 90023

Application / Permit
22010-10000-01988
Plan Check / Job No.
B22LA07134
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU 2-STORY (37.5'X18')
Permit Issued
Issued on 9/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 NGHI SU
Corrections Issued 6/2/2022 NGHI SU
Quality Review Completed 6/8/2022 KEN GILL
Building Plans Picked Up 6/13/2022 APPLICANT
Applicant returned to address corrections 8/5/2022 NGHI SU
Plan Check Approved 9/7/2022 NGHI SU
Issued 9/16/2022 APPLICANT
CofO in Progress 1/5/2024 FREDDIE RIVERA
Permit Finaled 1/7/2024 DEROLD HAUFF
CofO Issued 1/7/2024 DEROLD HAUFF
Permit Finaled 1/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/15/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/23/2022 CINDY QI
Sewer availability Cleared 6/23/2022 CINDY QI
Low Impact Development Cleared 6/29/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 6/29/2022 CINDY QI
Hydrant and Access approval Cleared 7/29/2022 LAVEON RIDER

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/11/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/11/2022 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/1/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/1/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/15/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/15/2023 Approved FREDDIE RIVERA
Green Building Rough 2/15/2023 Partial Inspection FREDDIE RIVERA
HVAC-Rough 2/15/2023 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 2/15/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 2/15/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 2/15/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 3/16/2023 Approved FREDDIE RIVERA
Green Building Rough 3/16/2023 Approved FREDDIE RIVERA
HVAC-Rough 3/16/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 3/16/2023 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 3/16/2023 Approved FREDDIE RIVERA
Insulation 3/22/2023 Corrections Issued FREDDIE RIVERA
Drywall Nailing 3/31/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/31/2023 Approved JOSEPH MCGARRY
Gas Test 6/23/2023 Partial Inspection FREDDIE RIVERA
Sewer 6/23/2023 Approved FREDDIE RIVERA
Verify Rec and Parks Fee Memo 6/23/2023 Partial Inspection FREDDIE RIVERA
Gas Test 6/28/2023 Partial Approval FREDDIE RIVERA
Underground Mechanical 6/28/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Final 12/12/2023 Approved FREDDIE RIVERA
Final 12/12/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 12/12/2023 Approved FREDDIE RIVERA
Green Building Final 12/12/2023 Approved FREDDIE RIVERA
HVAC-Final 12/12/2023 Approved FREDDIE RIVERA
MERV13>=Final 12/12/2023 Approved FREDDIE RIVERA
PLUMBING-Final 12/12/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Approved FREDDIE RIVERA
Service/Power Release 12/12/2023 Partial Inspection FREDDIE RIVERA
Smoke Detectors 12/12/2023 Approved FREDDIE RIVERA
Final 1/5/2024 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 1/5/2024 Approved FREDDIE RIVERA