4430 N HASKELL AVE 91436

Certificate Information: 4430 N HASKELL AVE 91436

Application / Permit
22010-10000-01949
Plan Check / Job No.
B22LA06958
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 2-STORY ACCESSORY LIVING QUARTER
Permit Issued
Issued on 3/31/2023
Issuing Office
Current Status
CofO in Progress on 4/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 ERIC WONG
Corrections Issued 5/7/2022 ERIC WONG
Quality Review Completed 5/12/2022 KEN GILL
Building Plans Picked Up 5/17/2022 APPLICANT
Applicant returned to address corrections 6/16/2022 ERIC WONG
Applicant returned to address corrections 10/20/2022 ERIC WONG
Plan Check Approved 1/27/2023 ERIC WONG
Issued 3/31/2023 APPLICANT
CofO in Progress 6/13/2025 THOMAS FINNILA
No Progress 4/25/2026 MICHAEL PELHAM
CofO in Progress 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/18/2022 CARLOS AGUILERA
Sewer availability Cleared 6/1/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/6/2022 KURT CORRAL
Grading Pre-Inspection Cleared 10/20/2022 ERIC WONG
Low Impact Development Cleared 1/13/2023 DEBORA LEITE
Roof/Waste drainage to street Cleared 1/18/2023 CARLOS AGUILERA

Contact Information

Contractor N C C Construction & Development Inc; Lic. No.: 1021608-B 2346 SHELBY AVE      LOS ANGELES, CA 90064
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/30/2023 Partial Approval VINCENT HANLEY
Sewer 6/30/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/26/2023 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/22/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/22/2024 Approved VINCENT HANLEY
Green Building Rough 4/22/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 4/22/2024 Approved VINCENT HANLEY
PLUMBING-Rough 4/22/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/22/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/2/2024 Corrections Issued HENRY KIM
Green Building Rough 5/2/2024 Corrections Issued HENRY KIM
Interior/Exterior Lathing 5/2/2024 Not Ready for Inspection HENRY KIM
Shower Pan 5/2/2024 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 5/8/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Approved VINCENT HANLEY
Green Building Rough 5/8/2024 Approved VINCENT HANLEY
Shower Pan 5/8/2024 Approved VINCENT HANLEY
Insulation 5/13/2024 Corrections Issued THOMAS FINNILA
Drywall Nailing 5/31/2024 Approved ARUTYUN MADATYAN
Final 5/12/2025 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/12/2025 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 5/12/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 5/22/2025 Not Ready for Inspection THOMAS FINNILA
Final 5/22/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 5/22/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 5/22/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 5/30/2025 Approved THOMAS FINNILA
HVAC-Final 5/30/2025 Approved THOMAS FINNILA
PLUMBING-Final 5/30/2025 Approved THOMAS FINNILA
Final 6/4/2025 Corrections Issued ROBERT GOLD
Green Building Final 6/4/2025 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Not Ready ROBERT GOLD
Service/Power Release 6/4/2025 Not Required ROBERT GOLD
Smoke Detectors 6/4/2025 Approved ROBERT GOLD
Final 6/12/2025 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved THOMAS FINNILA
Service/Power Release 6/12/2025 Not Required THOMAS FINNILA