246 1/2 E 118TH ST 90061

Certificate Information: 246 1/2 E 118TH ST 90061

Application / Permit
22010-10000-01947
Plan Check / Job No.
B22LA06957
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU WITH ATTACHED 4-CAR GARAGE per LAMC 12.22 A.33 (c)-(d) (REAR BUILDING).
Permit Issued
Issued on 12/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 MAHNAZ NOURHASHEMI
Corrections Issued 6/2/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 6/6/2022 SAI KHUM
Building Plans Picked Up 6/14/2022 APPLICANT
Plan Check Approved 8/9/2022 MAHNAZ NOURHASHEMI
Issued 12/13/2022 APPLICANT
CofO in Progress 7/24/2023 JOHN KLARIN
Permit Finaled 7/24/2023 ANSON MAGLASANG
CofO Issued 7/24/2023 ANSON MAGLASANG
Permit Finaled 7/24/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/22/2022 WALLIE JONG
Permit Cleared 6/22/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/28/2022 WALLIE JONG
Sewer availability Cleared 6/30/2022 WALLIE JONG
Hydrant and Access approval Cleared 7/16/2022 KURT CORRAL
Low Impact Development Cleared 7/20/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/1/2022 WALLIE JONG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Approved JAMES CHAVEZ
HVAC-Rough 5/4/2023 Approved JOHN KLARIN
PLUMBING-Rough 5/4/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/5/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 5/5/2023 Approved JOHN KLARIN
Green Building Rough 5/5/2023 Approved JOHN KLARIN
MERV13>=Rough 5/5/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 5/5/2023 Approved JOHN KLARIN
Insulation 5/10/2023 Approved JOHN KLARIN
Drywall Nailing 5/22/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 5/22/2023 Approved JOHN KLARIN
Sewer 6/15/2023 Approved JOHN KLARIN
Underground Mechanical 6/15/2023 Approved JOHN KLARIN
ELECTRICAL-Final 6/20/2023 Partial Approval JAMES CHAVEZ
ELECTRICAL-Final 7/21/2023 Approved JOHN KLARIN
Final 7/21/2023 OK to Issue CofO JOHN KLARIN
Green Building Final 7/21/2023 Approved JOHN KLARIN
HVAC-Final 7/21/2023 Approved JOHN KLARIN
MERV13>=Final 7/21/2023 Approved JOHN KLARIN
PLUMBING-Final 7/21/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 7/21/2023 Approved JOHN KLARIN
Smoke Detectors 7/21/2023 Approved JOHN KLARIN