629 E 116TH PL 90059
Certificate Information: 629 E 116TH PL 90059
- Application / Permit
- 22010-10000-01945
- Plan Check / Job No.
- B22LA06955
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU WITH ATTACHED 4-CAR GARAGE (REAR BUILDING)
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | JAD BASMA |
| Corrections Issued | 5/7/2022 | JAD BASMA |
| Quality Review Completed | 5/9/2022 | SAI KHUM |
| Building Plans Picked Up | 5/13/2022 | APPLICANT |
| Plan Check Approved | 5/24/2023 | JAD BASMA |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 12/8/2023 | JOHN KLARIN |
| Permit Finaled | 1/22/2024 | ANSON MAGLASANG |
| CofO Issued | 1/22/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/22/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/10/2022 | ANTHONY VARGAS |
| Address approval | Cleared | 5/27/2022 | CELINA MORENO |
| Address approval | Cleared | 5/27/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2022 | CELINA MORENO |
| Sewer availability | Cleared | 5/31/2022 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/24/2022 | KURT CORRAL |
| SB8 RUD | Cleared | 5/17/2023 | LOUIE MILLER |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/8/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 9/8/2023 | Approved | JOHN KLARIN |
| MERV13>=Rough | 9/8/2023 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 9/8/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 9/8/2023 | Approved | JOHN KLARIN |
| Insulation | 9/11/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 9/26/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/26/2023 | Approved | JOHN KLARIN |
| Sewer | 10/30/2023 | Approved | JOHN KLARIN |
| Underground Mechanical | 10/30/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 11/21/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 12/4/2023 | Approved | JOHN KLARIN |
| Final | 12/4/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/4/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 12/4/2023 | Approved | JOHN KLARIN |
| MERV13>=Final | 12/4/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 12/4/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 12/4/2023 | Approved | JOHN KLARIN |
| Smoke Detectors | 12/4/2023 | Approved | JOHN KLARIN |
| Final | 12/6/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 12/6/2023 | Approved | JOHN KLARIN |
| Final | 12/8/2023 | OK to Issue CofO | JOHN KLARIN |