1332-1334 E 49TH ST 90011

Certificate Information: 1332-1334 E 49TH ST 90011

Application / Permit
22010-10000-01941
Plan Check / Job No.
B22LA06919
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR.
Permit Issued
Issued on 9/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 KEVIN MORALES
Corrections Issued 5/4/2022 KEVIN MORALES
Quality Review Completed 5/5/2022 EUGENE BARBEAU
Building Plans Picked Up 5/10/2022 APPLICANT
Plan Check Approved 7/12/2022 KEVIN MORALES
Issued 9/6/2022 APPLICANT
CofO in Progress 4/17/2023 BRENDAN MORELLI
Permit Finaled 4/22/2023 DEROLD HAUFF
CofO Issued 4/22/2023 DEROLD HAUFF
Permit Finaled 4/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2022 STEVE MELGAR
Highway dedication Cleared 5/17/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/18/2022 STEVE MELGAR
Sewer availability Cleared 5/18/2022 STEVE MELGAR
Frnt yard landscape/Water mgmt Cleared 5/20/2022 ANACANY HURTADO
Low Impact Development Cleared 6/7/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 6/8/2022 STEVE MELGAR
SB8 RUD Cleared 7/1/2022 NICHOLAS KAWAZOE
Hydrant and Access approval Cleared 7/3/2022 RUEL COLE

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/15/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/15/2022 Partial Approval ALEJANDRO DE ARTOLA
Sewer 11/15/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 11/15/2022 Approved ALEJANDRO DE ARTOLA
Insulation 11/16/2022 Partial Approval SCOTT FINNILA
Wood Frame 11/16/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Approved BRENDAN MORELLI
ELECTRICAL-Rough 1/25/2023 Approved BRENDAN MORELLI
HVAC-Rough 1/25/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/26/2023 Approved BRENDAN MORELLI
Green Building Rough 1/26/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/26/2023 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 1/26/2023 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 1/26/2023 Approved BRENDAN MORELLI
Insulation 2/3/2023 Approved BRENDAN MORELLI
Drywall Nailing 2/16/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/16/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 3/28/2023 No Access for Inspection BRENDAN MORELLI
ELECTRICAL-Final 4/3/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 4/14/2023 Approved BRENDAN MORELLI
Final 4/14/2023 Conditional Approval BRENDAN MORELLI
Green Building Final 4/14/2023 Approved BRENDAN MORELLI
HVAC-Final 4/14/2023 Approved BRENDAN MORELLI
PLUMBING-Final 4/14/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Approved BRENDAN MORELLI
Service/Power Release 4/14/2023 Approved BRENDAN MORELLI
Smoke Detectors 4/14/2023 Approved BRENDAN MORELLI
Final 4/17/2023 OK to Issue CofO BRENDAN MORELLI
Service/Power Release 4/17/2023 Approved BRENDAN MORELLI
Service/Power Release 4/19/2023 Approved BRENDAN MORELLI