4017 E SEQUOIA ST 90039

Certificate Information: 4017 E SEQUOIA ST 90039

Application / Permit
22010-10000-01928
Plan Check / Job No.
B22LA06883
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER CA Govt. Code 65852.2(e)(1)(B) (1-STORY)
Permit Issued
Issued on 9/7/2023
Issuing Office
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 CARLOS MONTES
Corrections Issued 5/7/2022 CARLOS MONTES
Quality Review Completed 5/20/2022 MICHAEL PEREZ
Applicant returned to address corrections 5/10/2023 CARLOS MONTES
Applicant returned to address corrections 8/16/2023 CARLOS MONTES
Plan Check Approved 8/30/2023 CARLOS MONTES
Issued 9/7/2023 APPLICANT
CofO in Progress 1/24/2025 THOMAS LOGRASSO
CofO Issued 1/27/2025 DEROLD HAUFF
Permit Finaled 1/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/14/2022 JEANETTE VONG
Tenant Habitability Plan Cleared 6/23/2022 MICHAEL SOTO
Eng Process Fee Ord 176,300 Cleared 6/28/2022 JEANETTE VONG
Sewer availability Cleared 6/28/2022 JEANETTE VONG
Low Impact Development Cleared 7/25/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/27/2023 JEANIE LAM
Construction near power lines Cleared 8/9/2023 RIDWAN HARDY

Contact Information

Contractor X3build Inc; Lic. No.: 1065494-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/13/2024 Partial Approval SCOTT FINNILA
Pre-Inspection 3/13/2024 Partial Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 3/21/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/21/2024 Approved HAMIK HARTOUNIAN
Underground Mechanical 3/21/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/22/2024 Approved HAMIK HARTOUNIAN
Gas Test 5/2/2024 Partial Approval HAMIK HARTOUNIAN
Sewer 5/2/2024 Approved HAMIK HARTOUNIAN
Underground Mechanical 5/2/2024 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 5/13/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/31/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 5/31/2024 Approved THOMAS LOGRASSO
HVAC-Rough 5/31/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/4/2024 Conditional Approval THOMAS LOGRASSO
Shower Pan 6/4/2024 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 6/10/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/18/2024 Approved Pending GreenApproval ALIZAH MAYAGOITIA
Green Building Rough 6/18/2024 Approved ALIZAH MAYAGOITIA
Insulation 6/18/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/18/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/21/2024 Approved BRENDAN MORELLI
Service/Power Release 8/9/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 9/20/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/3/2024 Approved THOMAS LOGRASSO
Final 10/3/2024 Corrections Issued THOMAS LOGRASSO
Green Building Final 10/3/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 10/3/2024 Approved THOMAS LOGRASSO
Smoke Detectors 10/3/2024 Approved THOMAS LOGRASSO
Final 11/25/2024 No Access for Inspection THOMAS LOGRASSO
Special/Order Compliance 11/25/2024 Partial Inspection THOMAS LOGRASSO
Final 12/17/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 1/23/2025 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 1/23/2025 Approved THOMAS LOGRASSO