New detached Accessory Dwelling Unit at rear of property per GCS 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g). NFPA 13D sprinklers throughout
Permit Issued
Issued on 10/6/2022
Issuing Office
Current Status
CofO Issued on 4/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 MINYE PAK
Corrections Issued 4/25/2022 MINYE PAK
Plan Check Approved 10/6/2022 ALLEN MANALANSAN
Issued 10/6/2022 APPLICANT
CofO in Progress 4/17/2023 RUBEN SALAS
Permit Finaled 4/17/2023 RONALD MYRICK
CofO Issued 4/17/2023 RONALD MYRICK
Permit Finaled 4/17/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 4/25/2022 AMAAN MALIK
ZI Cleared 5/2/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 5/4/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 5/4/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 8/25/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/29/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Perez,, Michael; Lic. No.: C86432 201 N. FIGUEROA      LOS ANGELES, CA 90012

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/12/2022 Partial Approval BRIAN SULLIVAN
Sewer 10/12/2022 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/17/2022 Approved RUBEN SALAS
BUILDING-Rough-Frame 11/9/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 11/9/2022 Not Ready for Inspection RUBEN SALAS
Verify Sprinkler Sign Off 11/9/2022 Not Ready for Inspection RUBEN SALAS
Rough-Elec/Plmb/HVAC 11/22/2022 Corrections Issued RUBEN SALAS
Rough-Elec/Plmb/HVAC 12/7/2022 Approved RUBEN SALAS
Wood Frame 12/7/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 12/16/2022 Partial Approval RUBEN SALAS
Insulation 12/19/2022 Conditional Approval RUBEN SALAS
Drywall Nailing 12/22/2022 Approved RUBEN SALAS
Green Building Rough 12/22/2022 Approved RUBEN SALAS
Service/Power Release 1/3/2023 Corrections Issued RUBEN SALAS
ELECTRICAL-Final 2/16/2023 Approved RUBEN SALAS
Service/Power Release 2/16/2023 Approved RUBEN SALAS
BUILDING-Rough-Frame 3/16/2023 Approved RUBEN SALAS
Final 3/16/2023 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 3/16/2023 Approved RUBEN SALAS
Green Building Final 3/16/2023 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 3/16/2023 SGSOV Approved RUBEN SALAS
Smoke Detectors 3/16/2023 Approved RUBEN SALAS
Verify Sprinkler Sign Off 3/16/2023 Approved RUBEN SALAS
Final 4/14/2023 OK to Issue CofO RUBEN SALAS
Green Building Final 4/14/2023 Approved RUBEN SALAS