1526 W 220TH ST 90501

Certificate Information: 1526 W 220TH ST 90501

Application / Permit
22010-10000-01908
Plan Check / Job No.
B22LA06809
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD (MIDDLE) 2 OF 3
Permit Issued
Issued on 10/4/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 ADRIANA LOPEZ
Corrections Issued 5/8/2022 ADRIANA LOPEZ
Quality Review Completed 5/13/2022 FARUK SEZER
Building Plans Picked Up 9/8/2022 APPLICANT
Plan Check Approved 9/30/2022 ADRIANA LOPEZ
Issued 10/4/2022 APPLICANT
CofO in Progress 9/13/2023 EUGENE CASSIDY
CofO Issued 9/20/2023 ANSON MAGLASANG
Permit Finaled 9/20/2023 ANSON MAGLASANG

Permit Application Clearance Information

Low Impact Development Cleared 8/4/2022 MITESH PATEL
Address approval Cleared 8/11/2022 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 8/11/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 8/23/2022 JOSE HERNANDEZ
Hydrant and Access approval Cleared 9/8/2022 MATTHEW CRAIG
Sewer availability Cleared 9/8/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/24/2022 Partial Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved EUGENE CASSIDY
Footing/Foundation/Slab 10/28/2022 Approved EUGENE CASSIDY
METHANE-Barrier 10/28/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 10/28/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 12/19/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 12/19/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 12/19/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 12/19/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 12/19/2022 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 12/19/2022 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval EUGENE CASSIDY
HVAC-Rough 12/28/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 12/28/2022 Approved EUGENE CASSIDY
Wood Frame 12/28/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 1/17/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 1/17/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Approved EUGENE CASSIDY
Green Building Rough 1/17/2023 Approved EUGENE CASSIDY
HVAC-Rough 1/17/2023 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 1/17/2023 Approved EUGENE CASSIDY
Wood Frame 1/17/2023 Partial Approval EUGENE CASSIDY
Insulation 1/30/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 1/30/2023 Approved JOHN KLARIN
Drywall Nailing 2/6/2023 Approved EUGENE CASSIDY
Sewer 4/20/2023 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/31/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/31/2023 Approved EUGENE CASSIDY
Final 8/31/2023 Corrections Issued EUGENE CASSIDY
Green Building Final 8/31/2023 Approved EUGENE CASSIDY
HVAC-Final 8/31/2023 Approved EUGENE CASSIDY
PLUMBING-Final 8/31/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 8/31/2023 Approved EUGENE CASSIDY
Verify Rec and Parks Fee Memo 8/31/2023 Not Ready for Inspection EUGENE CASSIDY
Final 9/12/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 9/12/2023 Approved EUGENE CASSIDY
Service/Power Release 9/12/2023 Approved EUGENE CASSIDY