6128 E SPRINGVALE DR 90042
Certificate Information: 6128 E SPRINGVALE DR 90042
- Application / Permit
- 22010-10000-01892
- Plan Check / Job No.
- B22LA06744
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU AT REAR OF THE LOT (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d)). ALL WORK DONE PER ENGINEERING. ADU IS IN THE NORTHEAST LOS ANGELES COMMUNITY PLAN AREA. "COMPLY WITH DEPARTMENT ORDER effective date 07/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 920598.
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | ZAW HAN |
| Corrections Issued | 5/3/2022 | ZAW HAN |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Applicant returned to address corrections | 4/12/2023 | DANIEL SMILEY |
| Plan Check Approved | 4/19/2023 | JOSEPH RAFOLS |
| Issued | 4/19/2023 | APPLICANT |
| Permit Finaled | 9/30/2024 | DANIEL SANCHEZ |
| CofO Issued | 9/30/2024 | DANIEL SANCHEZ |
| Permit Finaled | 9/30/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 7/5/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2022 | CINDY QI |
| Sewer availability | Cleared | 7/21/2022 | CINDY QI |
| Certificate of Compliance | Cleared | 11/23/2022 | YINGSHI HUANG |
| Low Impact Development | Cleared | 3/29/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 3/30/2023 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 4/11/2023 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 4/12/2023 | DANIEL SMILEY |
Contact Information
| Contractor | Cgs Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Corrections Issued | RAUL VASQUEZ |
| PLUMBING-Rough | 6/16/2023 | Approved | RAUL VASQUEZ |
| Footing/Foundation/Slab | 7/3/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | Approved | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 9/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Gas Test | 9/12/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 9/12/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Rough-Elec/Plmb/HVAC | 9/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Sewer | 9/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 9/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| Insulation | 11/9/2023 | Approved | RAUL VASQUEZ |
| Interior/Exterior Lathing | 11/9/2023 | Approved | RAUL VASQUEZ |
| Drywall Nailing | 11/21/2023 | Approved | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 3/18/2024 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 3/18/2024 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Approved | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 3/18/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 3/18/2024 | Approved | DANIEL DELACRUZ |
| Sewer | 3/18/2024 | Approved | DANIEL DELACRUZ |
| Shower Pan | 3/18/2024 | Approved | DANIEL DELACRUZ |
| Verify Sprinkler Sign Off | 3/18/2024 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 4/3/2024 | Approved | DANIEL DELACRUZ |
| Final | 5/13/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Green Building Final | 5/13/2024 | Corrections Issued | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 5/13/2024 | SGSOV Not Ready | DANIEL DELACRUZ |
| Service/Power Release | 5/13/2024 | Approved | DANIEL DELACRUZ |
| Smoke Detectors | 5/13/2024 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Final | 5/15/2024 | Approved | DANIEL DELACRUZ |
| Final | 5/15/2024 | Conditional Approval | DANIEL DELACRUZ |
| Gas Test | 5/15/2024 | Approved | DANIEL DELACRUZ |
| Green Building Final | 5/15/2024 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 5/15/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 5/15/2024 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | DANIEL DELACRUZ |
| Final | 7/9/2024 | Corrections Issued | DANIEL DELACRUZ |
| Final | 9/4/2024 | Partial Approval | DANIEL DELACRUZ |