10345 W ILONA AVE 90064
Certificate Information: 10345 W ILONA AVE 90064
- Application / Permit
- 22010-10000-01881
- Plan Check / Job No.
- B22LA06725
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | MICHAEL LOPEZ |
| Corrections Issued | 6/10/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 6/17/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 9/13/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/21/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/3/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/10/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 6/12/2023 | MICHAEL LOPEZ |
| No Progress | 9/18/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 9/18/2023 | MICHAEL LOPEZ |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 7/19/2025 | DANIEL VERA |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
| CofO Issued | 7/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/15/2022 | ALEXANDER HELFER |
| Construction near power lines | Cleared | 10/28/2022 | PATRICK MAGALLANES |
| ZA Case | Cleared | 11/1/2022 | ASHLEY RODARTE |
| Address approval | Cleared | 11/5/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 11/7/2022 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 11/13/2022 | JOHN CONNEALLY |
| Specific Plan | Cleared | 11/14/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 2/13/2023 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 2/14/2023 | JASON NG |
| GPI Written Notices | Cleared | 6/12/2023 | TEODORO DIAZ RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 10/25/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/25/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Methane Barrier | 11/13/2023 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Subgrade | 11/15/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Subgrade | 11/20/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 1/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/26/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Barrier | 2/26/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 8/20/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 8/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 8/20/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/20/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/29/2024 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/29/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 8/29/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/29/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 8/29/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/8/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 10/8/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/8/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 10/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 10/22/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 11/18/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/18/2024 | Approved | STEPHANIE SWANSON |
| Final | 5/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 5/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Not Ready | ASHLEY THOMPSON |
| Service/Power Release | 5/30/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 5/30/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 6/10/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 6/10/2025 | Partial Approval | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Not Ready | DANIEL VERA |
| Service/Power Release | 6/10/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 6/10/2025 | Approved | DANIEL VERA |
| Final | 7/7/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 7/7/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Ready | DANIEL VERA |
| Service/Power Release | 7/7/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 7/18/2025 | OK to Issue CofO | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Approved | DANIEL VERA |
| Service/Power Release | 7/18/2025 | Approved | DANIEL VERA |