3875 S MARCASEL AVE 90066
Certificate Information: 3875 S MARCASEL AVE 90066
- Application / Permit
- 22010-10000-01870
- Plan Check / Job No.
- B22LA06680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY RESIDENCE WITH 2-CAR GARAGE AND ATTACHED TRELLIS'. 1 OF 2
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | ADRIANA LOPEZ |
| Corrections Issued | 4/30/2022 | ADRIANA LOPEZ |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| Quality Review Completed | 6/10/2022 | FARUK SEZER |
| Applicant returned to address corrections | 7/28/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 10/28/2022 | ADRIANA LOPEZ |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 11/6/2024 | JESUS PINEDA |
| CofO in Progress | 11/6/2024 | JESUS PINEDA |
| CofO in Progress | 11/19/2024 | JESUS PINEDA |
| CofO Issued | 11/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/16/2022 | VALERIA CEJA |
| Permit | Cleared | 6/21/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/21/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2022 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 7/21/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 8/3/2022 | SUNG JOON WON |
| Permit | Cleared | 8/5/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 9/1/2022 | ADALBERTO VERA |
| Disturb/Remove Protected Trees | Cleared | 10/18/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Aditan Inc; Lic. No.: 986364-B | 8025 DEERING AVE CANOGA PARK, CA 91304 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/31/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/7/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 6/12/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/12/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/1/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 8/10/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 8/15/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 8/15/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 8/18/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/18/2023 | Partial Approval | EVAN COOPER |
| Shower Pan | 8/18/2023 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 8/28/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/24/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/24/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 11/2/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 8/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 8/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/19/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/24/2024 | Approved | JESUS PINEDA |
| Final | 9/24/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 9/24/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 9/24/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 9/24/2024 | Approved | JESUS PINEDA |
| Final | 10/1/2024 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Not Ready | HERBERT GIRON |
| PLUMBING-Final | 10/3/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Approved | JESUS PINEDA |
| Final | 11/5/2024 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 11/5/2024 | Approved | JESUS PINEDA |