709 1/4 W 77TH ST 90044

Certificate Information: 709 1/4 W 77TH ST 90044

Application / Permit
22010-10000-01806
Plan Check / Job No.
B22LA06424
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 10/20/2022
Issuing Office
Current Status
Issued on 10/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 CARLOS MONTES
Corrections Issued 4/30/2022 CARLOS MONTES
Quality Review Completed 5/17/2022 MICHAEL PEREZ
Applicant returned to address corrections 6/30/2022 CARLOS MONTES
Applicant returned to address corrections 8/9/2022 CARLOS MONTES
Plan Check Approved 10/20/2022 CARLOS MONTES
Issued 10/20/2022 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/24/2022 ISMAEL HERNANDEZ
"Q" conditions Cleared 5/25/2022 MIGUEL GAMBOA
Low Impact Development Cleared 6/17/2022 ANTHONY VARGAS
Address approval Cleared 6/21/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/22/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 6/22/2022 JEANIE LAM
Sewer availability Cleared 6/22/2022 JEANIE LAM

Contact Information

Contractor Swami International Inc; Lic. No.: 833804-B       ,
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/20/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 12/23/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 12/23/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 1/19/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 1/27/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 1/27/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 1/27/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 2/2/2023 Approved LILIANA PORTILLO
HVAC-Rough 2/2/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 2/2/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/3/2023 Approved LILIANA PORTILLO
Green Building Rough 2/3/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/3/2023 Partial Approval LILIANA PORTILLO
Shower Pan 2/3/2023 Approved LILIANA PORTILLO
Insulation 2/7/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/7/2023 Approved LILIANA PORTILLO
Drywall Nailing 2/13/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/10/2023 Corrections Issued BRENDAN MORELLI
Final 10/10/2023 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 10/10/2023 Approved BRENDAN MORELLI
Gas Test 10/10/2023 Not Ready for Inspection BRENDAN MORELLI
Green Building Final 10/10/2023 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 10/10/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 10/10/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 10/10/2023 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 10/10/2023 Approved BRENDAN MORELLI
Final 10/18/2023 Corrections Issued MICHAEL LEWIS
Gas Test 10/18/2023 Corrections Issued MICHAEL LEWIS
Green Building Final 10/18/2023 Corrections Issued MICHAEL LEWIS
HVAC-Final 10/18/2023 Partial Inspection MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 10/18/2023 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Final 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 10/11/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Final 10/22/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 10/22/2024 Corrections Issued MICHAEL LEWIS
Final 12/9/2024 Corrections Issued MICHAEL LEWIS
Gas Test 12/9/2024 Approved MICHAEL LEWIS
Green Building Final 12/9/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 12/9/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 12/18/2024 Not Ready for Inspection JOHN QUINTANILLA
Final 12/23/2024 No Access for Inspection JOHN QUINTANILLA
Service/Power Release 12/23/2024 No Access for Inspection JOHN QUINTANILLA
Final 12/24/2024 Conditional Approval JOHN QUINTANILLA
Service/Power Release 12/24/2024 Approved JOHN QUINTANILLA
Final 3/12/2026 Not Ready for Inspection JOHN QUINTANILLA