4028 W 59TH PL 90043
Certificate Information: 4028 W 59TH PL 90043
- Application / Permit
- 22010-10000-01796
- Plan Check / Job No.
- B22LA06362
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N)DETACHED ADU PER CA GOV'T CODE 65852.2(e)(1)(B) and LAMC 12.22A.33(c)-(d),(g). WOOD FRAME CONSTRUCTION PER WFPP
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | HANS SANTIAGO |
| Corrections Issued | 4/25/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/2/2022 | RAHEL BEYENE |
| Applicant returned to address corrections | 6/3/2022 | RAHEL BEYENE |
| Plan Check Approved | 6/6/2022 | ZAW HAN |
| Issued | 6/8/2022 | APPLICANT |
| CofO in Progress | 7/14/2024 | JOSE MACIAS |
| CofO Issued | 10/10/2024 | RUBEN SALAS |
| Permit Finaled | 10/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/13/2022 | KIRK LINKLATER |
| Address approval | Cleared | 5/17/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/20/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 6/2/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 6/3/2022 | AMAAN MALIK |
Contact Information
| Contractor | Outliers Construction; Lic. No.: 1006087-B | 9056 OAK STREET BELLFLOWER, CA 90706 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 6/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| Pre-Inspection | 6/27/2022 | Not Ready for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/12/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 10/31/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 11/21/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/7/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/5/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/5/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/24/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 9/21/2023 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 9/21/2023 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 9/27/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 10/16/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/3/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 4/3/2024 | Corrections Issued | JOSE MACIAS |
| Final | 4/3/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 4/3/2024 | Approved | JOSE MACIAS |
| HVAC-Final | 4/3/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Final | 4/3/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 4/3/2024 | Corrections Issued | JOSE MACIAS |
| Verify Sprinkler Sign Off | 4/3/2024 | Approved | JOSE MACIAS |
| Final | 4/25/2024 | No Access for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 4/25/2024 | No Access for Inspection | JOSE MACIAS |
| Final | 4/26/2024 | Corrections Issued | JOSE MACIAS |
| Final | 7/8/2024 | OK to Issue CofO | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/8/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 7/8/2024 | Approved | JOSE MACIAS |