17219 W LUVERNE PL 91316

Certificate Information: 17219 W LUVERNE PL 91316

Application / Permit
22010-10000-01781
Plan Check / Job No.
B22LA06310
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached One Story ADU per LAMC 12.22 A.33 (c)-(d). NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 8/14/2023
Issuing Office
Current Status
CofO Issued on 1/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 SERGIO GUTIERREZ
Corrections Issued 6/3/2022 SERGIO GUTIERREZ
Quality Review Completed 6/3/2022 RODOLFO ARIAS
Applicant returned to address corrections 12/8/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 3/20/2023 SERGIO GUTIERREZ
Plan Check Approved 8/4/2023 SERGIO GUTIERREZ
Issued 8/14/2023 APPLICANT
CofO in Progress 6/2/2025 SEAN WIRCH
Permit Finaled 1/15/2026 MICHAEL PELHAM
CofO Issued 1/15/2026 MICHAEL PELHAM
Permit Finaled 1/15/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 6/15/2022 CARLOS AGUILERA
Street Frontage Cleared 6/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/16/2022 CARLOS AGUILERA
Sewer availability Cleared 6/16/2022 CARLOS AGUILERA
ZA Case Cleared 7/15/2022 YINGSHI HUANG
ZA Case Cleared 7/19/2022 YINGSHI HUANG
Hydrant and Access approval Cleared 8/13/2022 RUEL COLE
Low Impact Development Cleared 5/11/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 6/8/2023 JOHN LIN
GPI Written Notices Cleared 7/28/2023 RODOLFO ARIAS
Grading Pre-Inspection Cleared 7/28/2023 RODOLFO ARIAS

Contact Information

Contractor Gramercy Builders Inc; Lic. No.: 943331-B       ,
Contractor Gramercy Group Design And Build Inc The; Lic. No.: 943331-B       ,
Engineer Peek,, Justen N; Lic. No.: C76751 702 RIO GRANDE CT      BRENTWOOD, CA 94513

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/6/2023 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/15/2023 Partial Approval VINCENT HANLEY
Piling/Pier/Caisson 12/15/2023 Partial Approval VINCENT HANLEY
Piling/Pier/Caisson 1/19/2024 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 3/1/2024 Approved VINCENT HANLEY
PLUMBING-Rough 3/19/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/20/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/20/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 5/14/2024 Partial Approval THOMAS FINNILA
PLUMBING-Rough 5/20/2024 Partial Approval THOMAS FINNILA
Verify Sprinkler Sign Off 5/20/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 5/31/2024 Corrections Issued THOMAS FINNILA
HVAC-Rough 5/31/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 5/31/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 6/5/2024 Approved THOMAS FINNILA
HVAC-Rough 6/5/2024 Approved THOMAS FINNILA
PLUMBING-Rough 6/5/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/7/2024 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 6/7/2024 Partial Approval THOMAS FINNILA
Shower Pan 6/7/2024 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 6/7/2024 Approved THOMAS FINNILA
Insulation 6/13/2024 Corrections Issued MORRIS JACKSON
Drywall Nailing 6/18/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/18/2024 Approved MORRIS JACKSON
Sewer 8/16/2024 Approved SEAN WIRCH
BUILDING-Rough-Frame 10/17/2024 Approved THOMAS FINNILA
Final 10/17/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 10/17/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Not Ready THOMAS FINNILA
Final 12/10/2024 Not Ready for Inspection THOMAS FINNILA
Final 3/21/2025 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved THOMAS FINNILA
Service/Power Release 3/21/2025 Approved THOMAS FINNILA
Smoke Detectors 3/21/2025 Approved THOMAS FINNILA
Final 3/28/2025 Not Ready for Inspection THOMAS FINNILA
Final 4/7/2025 Corrections Issued THOMAS FINNILA
Final 4/24/2025 Conditional Approval THOMAS FINNILA
Final 6/3/2025 OK to Issue CofO SEAN WIRCH
Special/Order Compliance 6/5/2025 Corrections Issued SEAN WIRCH