1239 W 64TH ST 90044

Certificate Information: 1239 W 64TH ST 90044

Application / Permit
22010-10000-01777
Plan Check / Job No.
B22LA06308
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 10/6/2022
Issuing Office
Current Status
CofO Issued on 2/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/11/2022 SAMUEL GONZALEZ
Corrections Issued 5/12/2022 SAMUEL GONZALEZ
Building Plans Picked Up 5/24/2022 APPLICANT
Applicant returned to address corrections 6/18/2022 SAMUEL GONZALEZ
Plan Check Approved 8/7/2022 SHANGQIN XIE
Issued 10/6/2022 APPLICANT
CofO in Progress 2/10/2023 ENRIQUE MIRELES
CofO Issued 2/22/2023 DEROLD HAUFF
Permit Finaled 2/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/17/2022 JEANETTE VONG
Sewer availability Cleared 5/17/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 5/25/2022 JEANETTE VONG
Construction near power lines Cleared 7/20/2022 RIDWAN HARDY

Contact Information

Contractor Cal Retrofit; Lic. No.: 1022167-B       ,
Contractor U S Home Pros Inc; Lic. No.: 1022167-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2022 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/28/2022 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Approved ENRIQUE MIRELES
Sewer 11/7/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/16/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Approved ENRIQUE MIRELES
HVAC-Rough 11/16/2022 Approved ENRIQUE MIRELES
Light Gage Steel Frame 11/16/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/16/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/21/2022 Approved ENRIQUE MIRELES
HVAC-Rough 11/21/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/21/2022 Approved ENRIQUE MIRELES
Light Gage Steel Frame 11/21/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/21/2022 Approved ENRIQUE MIRELES
Insulation 11/28/2022 Approved ENRIQUE MIRELES
Drywall Nailing 12/2/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/13/2022 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 12/23/2022 Approved ENRIQUE MIRELES
Final 12/23/2022 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/23/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/23/2022 Approved ENRIQUE MIRELES
Final 1/4/2023 Not Ready for Inspection ENRIQUE MIRELES
Final 1/13/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 1/13/2023 Approved ENRIQUE MIRELES
Final 1/30/2023 Corrections Issued ENRIQUE MIRELES
Final 2/9/2023 OK to Issue CofO ENRIQUE MIRELES