10570 W BLYTHE AVE 90064

Certificate Information: 10570 W BLYTHE AVE 90064

Application / Permit
22010-10000-01761
Plan Check / Job No.
B22LA06251
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESORY DWELLING UNIT REAR. PER LAMC 12.22 A.33 (c)-(d) 2 OF 2
Permit Issued
Issued on 7/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ADRIANA LOPEZ
Corrections Issued 4/30/2022 ADRIANA LOPEZ
Quality Review Completed 5/12/2022 KEN GILL
Building Plans Picked Up 5/13/2022 APPLICANT
Applicant returned to address corrections 6/15/2022 ADRIANA LOPEZ
Applicant returned to address corrections 7/8/2022 ADRIANA LOPEZ
Plan Check Approved 7/12/2022 ADRIANA LOPEZ
Issued 7/13/2022 APPLICANT
CofO in Progress 3/12/2024 OGANES TARAKHCHYAN
Permit Finaled 3/18/2024 DANIEL ORRANTE
CofO Issued 3/18/2024 DANIEL ORRANTE
Permit Finaled 3/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 5/5/2022 VALERIA CEJA
Specific Plan Cleared 5/5/2022 VALERIA CEJA
Address approval Cleared 5/6/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 5/6/2022 CATHERINE ADROVER
Sewer availability Cleared 5/9/2022 CATHERINE ADROVER
Construction near power lines Cleared 5/18/2022 WALTER RAMIREZ
Construction within easement Cleared 5/18/2022 WALTER RAMIREZ
Hydrant and Access approval Cleared 5/18/2022 RUEL COLE
Low Impact Development Cleared 6/24/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 6/29/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/22/2022 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/22/2022 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 9/22/2022 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 9/22/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 10/5/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/11/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/31/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/31/2023 Approved JESUS RODRIGUEZ
Sewer 2/13/2023 Approved ASHLEY THOMPSON
Underground Mechanical 2/13/2023 Approved ASHLEY THOMPSON
HVAC-Rough 2/21/2023 Corrections Issued CLAYTON GRAHAM
Shower Pan 3/24/2023 Approved ASHLEY THOMPSON
HVAC-Rough 4/6/2023 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 4/6/2023 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 4/10/2023 Corrections Issued ASHLEY THOMPSON
Green Building Rough 4/10/2023 Approved ASHLEY THOMPSON
HVAC-Rough 4/10/2023 Approved ASHLEY THOMPSON
METHANE-Rough 4/10/2023 Approved ASHLEY THOMPSON
Verify Sprinkler Sign Off 4/10/2023 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 4/21/2023 Conditional Approval CLAYTON GRAHAM
Insulation 4/21/2023 Approved CLAYTON GRAHAM
Drywall Nailing 5/1/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 5/3/2023 Approved CLAYTON GRAHAM
Gas Test 8/24/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 2/23/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 2/23/2024 Corrections Issued OGANES TARAKHCHYAN
Service/Power Release 2/23/2024 Approved OGANES TARAKHCHYAN
Gas Test 2/26/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/27/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 2/27/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 2/27/2024 Approved OGANES TARAKHCHYAN
Final 3/12/2024 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 3/12/2024 Approved OGANES TARAKHCHYAN